We've captured the moments from FabCon & SQLCon that everyone is talking about, and we are bringing them to the community, live and on-demand. Starts on April 14th. Register now
Hello,
I would like to create the following Gantt Chart using the Charticulator tool:https://charticulator.com/app/index.html
I have the following sample data:
| Project | Start Date | End Date | Milestone Date | Milestone Status | Resource |
| Project 1 | 10.03.2022 | 24.09.2022 | 13.04.2022 | Done | Resource 1 |
| Project 2 | 10.01.2022 | 24.10.2022 | 13.05.2022 | Not Done | Resource 2 |
| Project 3 | 17.05.2022 | 24.11.2022 | 13.06.2022 | Late | Resource 1 |
| Project 4 | 21.01.2022 | 24.01.2023 | 13.07.2022 | Not Done | Resource 2 |
| Project 5 | 25.06.2022 | 28.11.2022 | 13.08.2022 | Done | Resource 2 |
Is that even possible?
Thank you!
Your sample data doesn't match the picture. The picture suggests that project 1 was put on hiatus and then restarted?
Hi @lbendlin , Thanks for noticing, that was a design misunderstanding. I fixed the image.
Still doesn't match. Your Project 1 shows three milestones in the picture but only one in the sample data.
You will need separate data points for Project Start/Project End and Milestones. For example:
let
Source = Table.FromRows(Json.Document(Binary.Decompress(Binary.FromText("i45WCijKz0pNLlEwVNJRMjTQMzDWMzIwMgJyjEz0DCxhHENjPQMTGMclPy8VSAWlFueXFiWnArXG6iAMMoIaZIhkEJCPZJApjOOXX6KAbpgRimHGIC3mSFpAhhkiG2YG4/gkluBxlQlIryGqqyAcY6hB5sS7yhSk3xTJbiMLNFdZ4AoroEGxAA==", BinaryEncoding.Base64), Compression.Deflate)), let _t = ((type nullable text) meta [Serialized.Text = true]) in type table [Project = _t, #"Start Date" = _t, #"End Date" = _t, #"Milestone Date" = _t, #"Milestone Status" = _t, Resource = _t]),
#"Unpivoted Other Columns" = Table.UnpivotOtherColumns(Source, {"Project", "Resource", "Milestone Status"}, "Attribute", "Value")
in
#"Unpivoted Other Columns"
Hi @lbendlin ,
I run your query to generate data, the result is this:
ProjectMilestone StatusResourceAttributeValue
| Project 1 | Done | Resource 1 | Start Date | 10.03.2022 |
| Project 1 | Done | Resource 1 | End Date | 24.09.2022 |
| Project 1 | Done | Resource 1 | Milestone Date | 13.04.2022 |
| Project 2 | Not Done | Resource 2 | Start Date | 10.01.2022 |
| Project 2 | Not Done | Resource 2 | End Date | 24.10.2022 |
| Project 2 | Not Done | Resource 2 | Milestone Date | 13.05.2022 |
| Project 3 | Late | Resource 1 | Start Date | 17.05.2022 |
| Project 3 | Late | Resource 1 | End Date | 24.11.2022 |
| Project 3 | Late | Resource 1 | Milestone Date | 13.06.2022 |
| Project 4 | Not Done | Resource 2 | Start Date | 21.01.2022 |
| Project 4 | Not Done | Resource 2 | End Date | 24.01.2023 |
| Project 4 | Not Done | Resource 2 | Milestone Date | 13.07.2022 |
| Project 5 | Done | Resource 2 | Start Date | 25.06.2022 |
| Project 5 | Done | Resource 2 | End Date | 28.11.2022 |
| Project 5 | Done | Resource 2 | Milestone Date | 13.08.2022 |
Still my question remains: is it possible to create that type of Gantt chart using the Charticulator tool?
If you have recently started exploring Fabric, we'd love to hear how it's going. Your feedback can help with product improvements.
A new Power BI DataViz World Championship is coming this June! Don't miss out on submitting your entry.
Share feedback directly with Fabric product managers, participate in targeted research studies and influence the Fabric roadmap.