Workday calculation

Hi Experts,

I have requirement to calculate workday per month. 

The Logic for workday calculation is:
Number of days per month minus public holidays, Saturdays, and Wednesdays. If a public holiday falls on a Wednesday, it should be additionally subtracted.

In the Master calender. I have a sepearet column to identify IsHoliday, IsSaturday and IsWednesday.

Attahced is the PBIX

Workdays.pbix

Thank you!



  • Hi puru85 
    Modify the formula of column isworkday to :

    Not work day =
     
     IF('MasterCalendar'[Date] IN VALUES('Public Holiday'[Date]) && MasterCalendar[Weekday Number] =4,2,
     IF('MasterCalendar'[Date] IN VALUES('Public Holiday'[Date]) ||  MasterCalendar[Weekday Number] =7 ||  MasterCalendar[Weekday Number] =4,1,0
     ))

    Result :

    modified pbix is attached

    If this post helps, then please consider Accepting it as the solution to help the other members find it more quickly.

     

5 Replies

  • puru85 

    is this what you want?

     

    Measure = COUNTROWS('MasterCalendar')-CALCULATE(COUNTROWS(MasterCalendar),FILTER(MasterCalendar,MasterCalendar[Weekday]="Wednesday"))-CALCULATE(COUNTROWS('Public Holiday'),FILTER('Public Holiday','Public Holiday'[Date]<=min('MasterCalendar'[Date])&&'Public Holiday'[Date]<=max('MasterCalendar'[Date])))
     
  • Step 0: I use your PBIX file.

     

    Step 1: I make 3 measures below.

    M_All Days = COUNTROWS('MasterCalendar')

    M_Holiday_Wed_Sat = COUNTROWS(FILTER('MasterCalendar','MasterCalendar'[IsHoliday]=TRUE()||'MasterCalendar'[IsSaturday]=TRUE()||'MasterCalendar'[IsWednesday]=TRUE()))

    M_Workdays = [M_All Days]-[M_Holiday_Wed_Sat]

     

    Step 2: I make a matrix below.

     

     

  • Hi puru85 

    You can add column to the calender like :

    Not work day =
     IF('MasterCalendar'[Date] IN VALUES('Public Holiday'[Date]) ||  MasterCalendar[Weekday Number] =7 ||  MasterCalendar[Weekday Number] =4,1,0)
    And measure :
    Workdays count Rita = COUNTROWS('MasterCalendar')-sum('MasterCalendar'[Not work day])
    Result:

    The pbix is attached

     

    If this post helps, then please consider Accepting it as the solution to help the other members find it more quickly.

    • Ritaf1983's avatar
      Ritaf1983
      Super User

      Hi puru85 
      Modify the formula of column isworkday to :

      Not work day =
       
       IF('MasterCalendar'[Date] IN VALUES('Public Holiday'[Date]) && MasterCalendar[Weekday Number] =4,2,
       IF('MasterCalendar'[Date] IN VALUES('Public Holiday'[Date]) ||  MasterCalendar[Weekday Number] =7 ||  MasterCalendar[Weekday Number] =4,1,0
       ))

      Result :

      modified pbix is attached

      If this post helps, then please consider Accepting it as the solution to help the other members find it more quickly.

       

  • Hi Ritaf1983 mickey64 ryan_mayu ,

    Thank you for helping me.
    The measure you have created is calculating:
    Number of days per month minus public holidays, Saturdays, and Wednesdays.

    But requirement is:
    Number of days per month minus public holidays, Saturdays, and Wednesdays. If a public holiday falls on a Wednesday, it should be additionally subtracted.

    Please refer to below Master Calender Table for May 2024.

    1 May and 22 May is Public Holiday which falls on Wednesday so it should be additionally subtracted.

    So the number of working days for May 2024 will be: 20.