Workday calculation
Hi Experts,
I have requirement to calculate workday per month.
The Logic for workday calculation is:
Number of days per month minus public holidays, Saturdays, and Wednesdays. If a public holiday falls on a Wednesday, it should be additionally subtracted.
In the Master calender. I have a sepearet column to identify IsHoliday, IsSaturday and IsWednesday.
Attahced is the PBIX
Workdays.pbix
Thank you!
Hi puru85
Modify the formula of column isworkday to :Not work day =IF('MasterCalendar'[Date] IN VALUES('Public Holiday'[Date]) && MasterCalendar[Weekday Number] =4,2,IF('MasterCalendar'[Date] IN VALUES('Public Holiday'[Date]) || MasterCalendar[Weekday Number] =7 || MasterCalendar[Weekday Number] =4,1,0))Result :
modified pbix is attachedIf this post helps, then please consider Accepting it as the solution to help the other members find it more quickly.
5 Replies
- ryan_mayuSuper User
is this what you want?
Measure = COUNTROWS('MasterCalendar')-CALCULATE(COUNTROWS(MasterCalendar),FILTER(MasterCalendar,MasterCalendar[Weekday]="Wednesday"))-CALCULATE(COUNTROWS('Public Holiday'),FILTER('Public Holiday','Public Holiday'[Date]<=min('MasterCalendar'[Date])&&'Public Holiday'[Date]<=max('MasterCalendar'[Date]))) - mickey64Super User
Step 0: I use your PBIX file.
Step 1: I make 3 measures below.
M_All Days = COUNTROWS('MasterCalendar')
M_Holiday_Wed_Sat = COUNTROWS(FILTER('MasterCalendar','MasterCalendar'[IsHoliday]=TRUE()||'MasterCalendar'[IsSaturday]=TRUE()||'MasterCalendar'[IsWednesday]=TRUE()))
M_Workdays = [M_All Days]-[M_Holiday_Wed_Sat]
Step 2: I make a matrix below.
- Ritaf1983Super User
Hi puru85
You can add column to the calender like :
Not work day =IF('MasterCalendar'[Date] IN VALUES('Public Holiday'[Date]) || MasterCalendar[Weekday Number] =7 || MasterCalendar[Weekday Number] =4,1,0)And measure :Workdays count Rita = COUNTROWS('MasterCalendar')-sum('MasterCalendar'[Not work day])Result:The pbix is attached
If this post helps, then please consider Accepting it as the solution to help the other members find it more quickly.
- Ritaf1983Super User
Hi puru85
Modify the formula of column isworkday to :Not work day =IF('MasterCalendar'[Date] IN VALUES('Public Holiday'[Date]) && MasterCalendar[Weekday Number] =4,2,IF('MasterCalendar'[Date] IN VALUES('Public Holiday'[Date]) || MasterCalendar[Weekday Number] =7 || MasterCalendar[Weekday Number] =4,1,0))Result :
modified pbix is attachedIf this post helps, then please consider Accepting it as the solution to help the other members find it more quickly.
- puru85Helper II
Hi Ritaf1983 mickey64 ryan_mayu ,
Thank you for helping me.
The measure you have created is calculating:
Number of days per month minus public holidays, Saturdays, and Wednesdays.
But requirement is:
Number of days per month minus public holidays, Saturdays, and Wednesdays. If a public holiday falls on a Wednesday, it should be additionally subtracted.
Please refer to below Master Calender Table for May 2024.
1 May and 22 May is Public Holiday which falls on Wednesday so it should be additionally subtracted.
So the number of working days for May 2024 will be: 20.