I need to be able to calculated expected task completion percentage based on TODAY. Eg on Day 3 of a 10 day task, it should be 30% complete in theory. I need a fomula that calculates the current expected completion that changes on a day to day basis? Once I have this I can then compare with actual completion and add to my RAG rating.
Many thanks
Hi Wharfey ,
You can create column like DAX below.
expected_completion %=DIVIDE(DATEDIFF( [start_date], TODAY(), DAY), DATEDIFF( [start_date], [finish_date], DAY))
Best Regards,
Amy
Community Support Team _ Amy
If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.
3 Replies
- Tahreem24Super User
Wharfey , Welcome to Power BI Community!
You want something like below Screen shot? if yes so use the below Measure and set it data format to %.
Task Completed = Sum('Table'[Day])/CALCULATE(sum('Table'[Day]),ALL('Table'[Day]))Please don't forget to hit THUMBS UP and Accept this as a solution if it helps you!- WharfeyFrequent Visitor
Hi Tahreem
This is the kind of table view I'm after (below) so essentially all I need is a formula to calculate column E based on the TODAY() function that counts back to the start date and calculates what the percentage completion should be as of the current date. I will then use DAX to determine the Task_Health rating.
thanks again.
- v-xicaiCommunity Support
Hi Wharfey ,
You can create column like DAX below.
expected_completion %=DIVIDE(DATEDIFF( [start_date], TODAY(), DAY), DATEDIFF( [start_date], [finish_date], DAY))