Hi Wharfey ,
You can create column like DAX below.
expected_completion %=DIVIDE(DATEDIFF( [start_date], TODAY(), DAY), DATEDIFF( [start_date], [finish_date], DAY))
Best Regards,
Amy
Community Support Team _ Amy
If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.
Hi Tahreem
This is the kind of table view I'm after (below) so essentially all I need is a formula to calculate column E based on the TODAY() function that counts back to the start date and calculates what the percentage completion should be as of the current date. I will then use DAX to determine the Task_Health rating.
thanks again.
Hi Wharfey ,
You can create column like DAX below.
expected_completion %=DIVIDE(DATEDIFF( [start_date], TODAY(), DAY), DATEDIFF( [start_date], [finish_date], DAY))
Best Regards,
Amy
Community Support Team _ Amy
If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.