Project Management Report - Task Completion
- 6 years ago
Hi Wharfey ,
You can create column like DAX below.
expected_completion %=DIVIDE(DATEDIFF( [start_date], TODAY(), DAY), DATEDIFF( [start_date], [finish_date], DAY))
Best Regards,
Amy
Community Support Team _ Amy
If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.
Wharfey , Welcome to Power BI Community!
You want something like below Screen shot? if yes so use the below Measure and set it data format to %.
Hi Tahreem
This is the kind of table view I'm after (below) so essentially all I need is a formula to calculate column E based on the TODAY() function that counts back to the start date and calculates what the percentage completion should be as of the current date. I will then use DAX to determine the Task_Health rating.
thanks again.
- v-xicai6 years ago
Community Support
Hi Wharfey ,
You can create column like DAX below.
expected_completion %=DIVIDE(DATEDIFF( [start_date], TODAY(), DAY), DATEDIFF( [start_date], [finish_date], DAY))
Best Regards,
Amy
Community Support Team _ Amy
If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.