Skip to main content
cancel
Showing results for 
Search instead for 
Did you mean: 

To celebrate FabCon Vienna, we are offering 50% off select exams. Ends October 3rd. Request your discount now.

Reply
stuartharvey
Regular Visitor

gantt chart visual start and end date

I have downloaded the Gant Chart visual and started to build out a report based on data from MS Project Online.

I checked Project Name, Start Date, Finish, Date and % Complete (see visual)

My problem is the start and end dates seen in the data do not reflect in the gantt chart and for the life of me i cant figure out why.

First time poster so any help appreciated. 

 

 

6 REPLIES 6
andrewnorris
New Member

Are you still havI having issues with this? I had the same problem in powerBI but managed to rectify by using the desktop client, connecting to my PWA site and then creating a new column to rectify the fact the gantt visual multiplies by 8. Let me know if you are still having issues.

 

Thanks for the comment @andrewnorris, I'm a bit of a novice with this.

I tried to connect the desktop app with PWA using O365 credentials but was unsucessful, I'm having my IT team look at it for me, but when/if I manage to connect how do I go about adding a new colum?

Hi - I am having the same problem. I am new to Power BI so not sure how to create a new column. 

stuartharvey
Regular Visitor

First time user of Power BI and need some help.

I have sucesfully connected MS Project Online and am pulling in all the right data (as far as I can tell) and all is working well, Project Name, Start Date, Finish Date, % Complete and Owner (PM).

 

There is however one exception and I just cant figure it out.

 

The duration shown in MS Project is being multiplied by 8 (hours) therefore extending the timelines by decades, an example is shown in the screen shot

 

MS Project duration = 622d

Power BI duration = 4976

 

4976/8 = 622

 

Any help greatly appreciated

 

bi.PNG

v-qiuyu-msft
Community Support
Community Support

Hi @stuartharvey,

 

How does the table imported in Power BI desktop look like? Can you share some sample data about Project Name, Start Date, Finish, Date and % Complete?

 

You can follow this blog to create a Gantt chart: Visual Awesomeness Unlocked – Gantt chart. By the way, please try to run the latest desktop version 2.48.4792.481 64-bit (July 2017) to create the report.

 

Best Regards,
QiuyunYu

Community Support Team _ Qiuyun Yu
If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.

Hi @v-qiuyu-msft

 

Thanks for the reply, I have'nt imported a table I jhave just linked it to the MS Project site, where the data is held in various project plans, out put is seen in the screen shot.

 

I did this in the BI online version as I was unable to connect MS Project using the desktiop version.

 

I downloaded the visual based on the article you mentioned and followed that and a few different articles guidance, as mentioned I have it all working ok its just this duration conversion that seems to be an issue, I cant understand why it would take the stated duration and multiply by 8???

Helpful resources

Announcements
September Power BI Update Carousel

Power BI Monthly Update - September 2025

Check out the September 2025 Power BI update to learn about new features.

August 2025 community update carousel

Fabric Community Update - August 2025

Find out what's new and trending in the Fabric community.

Top Solution Authors
Top Kudoed Authors