Forum Discussion
ScottKC
2 years agoFrequent Visitor
Scheduled refresh Failure help
Hi and thanks, Our PBIS environment is a Premium Capacity P1. We have around 40 semantic models that most refresh each morning from 5am-8am, but a couple that also refresh hourly during business ...
aj1973
2 years agoCommunity Champion
Hi ScottKC
If this event happened once then no need to worry as it was an internal error that caused the failure but if it happens continually then the semantic might need a tune up or scale up the capacity.
ScottKC
2 years agoFrequent Visitor
Thanks for the reply. However, this doesn't explain why the failed jobs started at very odd times outside of their hourly schedule. I.E. the last job on the 18/12/2023 had the job starting at "18/12/2023 18:00:09" and ended at "18/12/2023 18:10:03".
The next couple of jobs the next morning started and finished as expected, but then something started at "18/12/2023 22:30:08" and is associated with the 9am hourlry scheduled on the 19th. I have no idea what or why.