kennykhor
Advocate I
Advocate I

Schedule refresh error at Workspace but no error with local PC refresh

My report hosted in Power BI webspace hit error today and keep prompting "Type mismatch" for a particular table loaded from Excel file. I have no problem to refresh this same table in my local PC, however the workspace copy is hitting error, which was working fine earlier.

 

kennykhor_0-1739339132506.png

 

Can someone please shed light on how to determine the root cause? Since no error arising from the report when refresh in local PC. For info, the Excel file is stored in sharepoint, both workspace and local copy are refreshing from the Excel file in the sharepoint.

1 ACCEPTED SOLUTION

Oh, then it would be possible, your source file column datatype have been updated
Try this, refresh it on desktop and publish that file on service replacing existing one


If this post helps, then please consider Accept it as the solution, Appreciate your Kudos!!
Proud to be a Super User!!

View solution in original post

5 REPLIES 5
arvindsingh802
Super User
Super User

Please confirm  Privacy level of your data source, update the web privacy level same as your desktop file and you should be good.


If this post helps, then please consider Accept it as the solution, Appreciate your Kudos!!
Proud to be a Super User!!

Hi, I just checked, both are set to "Organizational". For info, the data refresh is working fine till yesterday, and there is no change on it recently.

 

kennykhor_0-1739339988478.png

 

Oh, then it would be possible, your source file column datatype have been updated
Try this, refresh it on desktop and publish that file on service replacing existing one


If this post helps, then please consider Accept it as the solution, Appreciate your Kudos!!
Proud to be a Super User!!

I added a "Change Type" step, and notice there're some errors indicated on the pre-determined date columns. After standardized the date value, manage to refresh the schedule without error now. Thanks for valuable advice.

Great, please accept the applicable answer as solution to help others in future.


If this post helps, then please consider Accept it as the solution, Appreciate your Kudos!!
Proud to be a Super User!!

Helpful resources

Announcements
PBIApril_Carousel

Power BI Monthly Update - April 2025

Check out the April 2025 Power BI update to learn about new features.

Notebook Gallery Carousel1

NEW! Community Notebooks Gallery

Explore and share Fabric Notebooks to boost Power BI insights in the new community notebooks gallery.

April2025 Carousel

Fabric Community Update - April 2025

Find out what's new and trending in the Fabric community.

Top Solution Authors