Forum Discussion
piyushj
9 years agoFrequent Visitor
Power Bi Service Refresh - timeout expiration issue
Hi PBI Team, We are facing an issue in power bi service as well as in desktop app. We have huge amount of data available in tables (>10GB). We are importing data using SQL Server database. Previo...
Anonymous
7 years agoNot applicable
Also, I have got this confirmation from Microsoft team that there is a limit on query timeout of 5 hours. Since I was using SAP HANA DB and there is a query which runs for 10+ hours. It runs fine on Desktop, but fails on Service due to this timeout issue. Regards
GilbertQ
7 years agoSuper User
Hi there
That is correct, you have to make sure it finishes within the 5 hours to get it refreshing.
That is correct, you have to make sure it finishes within the 5 hours to get it refreshing.