Hi everyone,   I have a dataset requires to be refreshed once per hour. Normally it tooks 15-17 mins to complete refresh process, but sometime the previous refresh will takes more than an hour to r...
  • Icey's avatar
    6 years ago

    Hi Anonymous ,

    Based on my knowledge, there are 2 situations:

    1. If the scheduled refresh at 3:00 PM starting time is after 3:15 PM, the refresh will proceed, but the specific delay time is uncertain.

    2. If the scheduled refresh at 3:00 PM starting time is before 3:15 PM, the refresh will be canceled.

    You can see the refresh details in Refresh History.

    As long as the number of refreshes does not reach the upper limit, Power BI will always try to refresh.

     