Forum Discussion
Scheduled Refresh Error
- 8 years ago
While working with a helpful Microsoft employee, we found an entry in a log file that permissions were needed on a subdirectory inside the powerbi dir. Once this was granted to the service account things are working.
We tested this on another power bi report server and are getting the same behavior. Looking for a fix soon, otherwise we will have to reinstall the old version.
Hey samgreene1, couple questions for you:
1. Is this a clean install of report server or are you upgrading/migrating a previous install?
2. It wasn't clear from the post are you getting the error when you try to create the schedule or when you try to execute and existing one?
3. Are you able to share with me the RSPortal_XXXXX.log with me view private message?
4. This did work previously with the Oct. release of PBIRS?
Also one thing you can try is create a URL reservation that is not https and see if you get the error there. Thanks!
Matt M.