Gantt Chart Half Days

Hello,   I am trying to create a gantt chart to display a construction schedule. We occasionally have tasks which take 12h, or half a day assuming 24h work.   My dataset recognizes that the task ...
  • v-henryk-mstf's avatar
    4 years ago

    Hi jmiller2224 ,

     

    According to your description, just change Days to Hours in the Format-General-Duration unit. Refer to the following test results:


    If the problem is still not resolved, please provide detailed error information and let me know immediately. Looking forward to your reply.


    Best Regards,
    Henry


    If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.