Unpivot/transform data for use in Gantt Chart 2.2.3

Hi,   I would like to use the Gantt 2.2.3 visual in a report. However, I am struggling to get the data transformed in the right way.    To use the Gantt 2.2.3 I need to transform the data from a ...
  • nickvanmaele's avatar
    3 years ago

    hi Nielf 

     

    Perhaps first a remark about your input data. Being a project manager myself, if a milestone falls in the middle of a task, I usually create different tasks, one for the task preceding the milestone, and one for the task following the milestone. A milestone usually means that something is finished and another thing can then start.

     

    In other words, you might want to consider changing your base data for Task 1 to something like this: 

     

    TaskStart DateEnd DateMilestone?
    Task 1a2020-10-012020-11-04 
    Milestone 12020-11-042020-11-04Yes
    Task 1b2020-11-042023-02-10 
    Milestone 22023-02-102023-02-10Yes
    Task 1c2023-02-102023-10-16 
    Milestone 32023-10-162023-10-16Yes

     

    Now, to give a straight answer to your question, have a look at the Power Query code below:

    (the Source step looks complicated simply because I used the "Enter Data" functionality)

     

    let
    Source = Table.FromRows(Json.Document(Binary.Decompress(Binary.FromText("i45WCkkszlYwVNJRMjIwMtA1NNA1gHKMQRxDM7iMoa6BCUzGwAgoqRSrA9VuBBE30jWw1DU0giuyACKYDNAsY0Mk7UBbYmMB", BinaryEncoding.Base64), Compression.Deflate)), let _t = ((type nullable text) meta [Serialized.Text = true]) in type table [Column1 = _t, Column2 = _t, Column3 = _t, Column4 = _t, Column5 = _t]),
    #"Changed Type" = Table.TransformColumnTypes(Source,{{"Column1", type text}, {"Column2", type date}, {"Column3", type date}, {"Column4", type date}, {"Column5", type date}}),
    #"Renamed Columns" = Table.RenameColumns(#"Changed Type",{{"Column1", "Task"}, {"Column2", "Start Date"}, {"Column3", "End Date"}, {"Column4", "Milestone 1"}, {"Column5", "Milestone 2"}}),

    //take a copy of the above data and process it some more to create a table with tasks that are not milestones
    #"Original Data" = #"Renamed Columns",
    #"Removed Columns1" = Table.RemoveColumns(#"Original Data",{"Milestone 1", "Milestone 2"}),
    TableOfTasks = Table.AddColumn(#"Removed Columns1", "Milestone", each ""), //this is data that we will need later

     

    //now continue to work on the data from the #"Renamed Columns" step to create a table with tasks that are milestones
    #"Unpivoted Other Columns" = Table.UnpivotOtherColumns(#"Renamed Columns", {"Task", "Start Date", "End Date"}, "Attribute", "Value"),
    #"Replaced Start Date" = Table.ReplaceValue(#"Unpivoted Other Columns",each [Start Date],each [Value],Replacer.ReplaceValue,{"Start Date"}),
    #"Replaced End Date" = Table.ReplaceValue(#"Replaced Start Date",each [End Date],each [Value],Replacer.ReplaceValue,{"End Date"}),
    #"Removed Columns" = Table.RemoveColumns(#"Replaced End Date",{"Value"}),
    TableOfMilestones = Table.RenameColumns(#"Removed Columns",{{"Attribute", "Milestone"}}),

     

    //now append the tables with tasks and the table with milestones
    #"Appended Query" = Table.Combine({TableOfTasks, TableOfMilestones}),

     

    //and sort the whole thing to get the final table
    #"Sorted Rows" = Table.Sort(#"Appended Query",{{"Task", Order.Ascending}, {"Start Date", Order.Ascending}})
    in
    #"Sorted Rows"

     

    If this answer solves your problem, please indicate it as such.