Forecasting error

I am trying to build a forecast on two values using the Power BI custom forecasting visual. One is in seconds and I am receiving the error "Not enough data points". How do I solve this?

1 ACCEPTED SOLUTION

As far as I understand, you should specify more than 7 points.

 

Ignat Vilesov,

Software Engineer

 

Microsoft Power BI Custom Visuals

[email protected]

View solution in original post

3 REPLIES 3
v-viig
Community Champion
Community Champion

Hello @tylerbauer,

 

You should provide more data points to the visual in order to forecast other values.

 

Ignat Vilesov,

Software Engineer

 

Microsoft Power BI Custom Visuals

[email protected]

Hi Ignat,

 

Thanks for your response. Do you know the minimum number of data points required to display the forecasting visual?

 

Cheers, 

Tyler

As far as I understand, you should specify more than 7 points.

 

Ignat Vilesov,

Software Engineer

 

Microsoft Power BI Custom Visuals

[email protected]

Helpful resources

Announcements
Fabric Data Days is here Carousel

Data Days 2026

Don't miss out on Data Days, June 15 through August 7. Learn Fabric, Power BI, SQL, AI and more.

Power BI DataViz World Championships carousel

Power BI DataViz World Championships - June 2026

A new Power BI DataViz World Championship is coming this June! Don't miss out on submitting your entry.