percent of progress

Hi,

I have a date field called start date, I have a date field called end date, which formula can I use in dax to calculate the % of progress based on today date?

For example I started an activity on 1st of may, today is the 3rd may, the end date is 4of may and today I'm at 75% of progress.

Thank you

1 ACCEPTED SOLUTION
Jihwan_Kim
Super User
Super User

Hi, @Giada_Togliatti 

I tried to create a sample pbix file based on your explanation.

Please check the below picture and the sample pbix file's link down below, whether it suits your case.

Or, share your sample pbix file's link here, then I can try to look into it to come up with a more relevant measure.

 

 

Picture1.png

 

Activity Progress =
VAR activitystart =
MAX ( Activities[StartDate] )
VAR activityend =
MAX ( Activities[Enddate] )
VAR selecteddate =
MAX ( Dates[Date] )
VAR activitytotaldays = activityend - activitystart + 1
RETURN
SWITCH (
TRUE (),
activityend <= selecteddate, 1,
activitystart <= selecteddate
&& activityend > selecteddate,
( selecteddate - activitystart + 1 ) / activitytotaldays,
activitystart > selecteddate, 0
)

 

 

https://www.dropbox.com/s/m5nceut2vqfqimp/giada%20togliatti.pbix?dl=0 

 

Hi, My name is Jihwan Kim.

 

If this post helps, then please consider accept it as the solution to help other members find it faster, and give a big thumbs up.

 

Linkedin: linkedin.com/in/jihwankim1975/

Twitter: twitter.com/Jihwan_JHKIM


If this post helps, then please consider accepting it as the solution to help other members find it faster, and give a big thumbs up.


Click here to visit my LinkedIn page

Click here to schedule a short Teams meeting to discuss your question.

View solution in original post

6 REPLIES 6
Jihwan_Kim
Super User
Super User

Hi, @Giada_Togliatti 

I tried to create a sample pbix file based on your explanation.

Please check the below picture and the sample pbix file's link down below, whether it suits your case.

Or, share your sample pbix file's link here, then I can try to look into it to come up with a more relevant measure.

 

 

Picture1.png

 

Activity Progress =
VAR activitystart =
MAX ( Activities[StartDate] )
VAR activityend =
MAX ( Activities[Enddate] )
VAR selecteddate =
MAX ( Dates[Date] )
VAR activitytotaldays = activityend - activitystart + 1
RETURN
SWITCH (
TRUE (),
activityend <= selecteddate, 1,
activitystart <= selecteddate
&& activityend > selecteddate,
( selecteddate - activitystart + 1 ) / activitytotaldays,
activitystart > selecteddate, 0
)

 

 

https://www.dropbox.com/s/m5nceut2vqfqimp/giada%20togliatti.pbix?dl=0 

 

Hi, My name is Jihwan Kim.

 

If this post helps, then please consider accept it as the solution to help other members find it faster, and give a big thumbs up.

 

Linkedin: linkedin.com/in/jihwankim1975/

Twitter: twitter.com/Jihwan_JHKIM


If this post helps, then please consider accepting it as the solution to help other members find it faster, and give a big thumbs up.


Click here to visit my LinkedIn page

Click here to schedule a short Teams meeting to discuss your question.

@Jihwan_Kim , thank you for the reply, it works.

I want to create a filter too that shows the activity that are finished today (100%) and activity that are not finished, how can I do?

Hi, @Giada_Togliatti 

Thank you for your feedback.

I am not sure if I understood your question correctly.

Please check the below picture and the link.

Or, please let me have an idea about how your desirable slicer looks like. Then I can try to create it.

 

Activity Progress on Today =
VAR activitystart =
MAX ( Activities[StartDate] )
VAR activityend =
MAX ( Activities[Enddate] )
VAR selecteddate =
TODAY()
VAR activitytotaldays = activityend - activitystart + 1
RETURN
SWITCH (
TRUE (),
activityend <= selecteddate, 1,
activitystart <= selecteddate
&& activityend > selecteddate,
( selecteddate - activitystart + 1 ) / activitytotaldays,
activitystart > selecteddate, 0
)
 
 Picture1.png
 
 

If this post helps, then please consider accepting it as the solution to help other members find it faster, and give a big thumbs up.


Click here to visit my LinkedIn page

Click here to schedule a short Teams meeting to discuss your question.

@Jihwan_Kim , thank you for the reply, the measure is correct, but what I need is a slicer where I can choose between completed activity ( where the measure is 100%) or not completed activity, I need to be able to choose between the 2 option, something like this image but with the 2 option completed and not completed instead of activity.

Immagine.png

Hi, @Giada_Togliatti 

Please check the below picture and the measure that I used for the below visualization.

I created a new table (Slicer Table, disconnected table) in order to create a slicer. 

 

Picture1.png

 

Activity Progress on Today by group =
IF (
ISFILTERED ( Activities[Activity] ),
SUMX (
FILTER (
VALUES ( Activities[Activity] ),
COUNTROWS (
FILTER (
Slicer,
[Activity Progress on Today] >= Slicer[Min]
&& [Activity Progress on Today] < Slicer[Max]
)
) = 1
),
[Activity Progress on Today]
)
)

 

 

https://www.dropbox.com/s/m5nceut2vqfqimp/giada%20togliatti.pbix?dl=0 

 

 

Hi, My name is Jihwan Kim.

 

If this post helps, then please consider accept it as the solution to help other members find it faster, and give a big thumbs up.

 

Linkedin: linkedin.com/in/jihwankim1975/

Twitter: twitter.com/Jihwan_JHKIM


If this post helps, then please consider accepting it as the solution to help other members find it faster, and give a big thumbs up.


Click here to visit my LinkedIn page

Click here to schedule a short Teams meeting to discuss your question.

thank you!

Helpful resources

Announcements
Power BI DataViz World Championships

Power BI Dataviz World Championships

The Power BI Data Visualization World Championships is back! Get ahead of the game and start preparing now!

December 2025 Power BI Update Carousel

Power BI Monthly Update - December 2025

Check out the December 2025 Power BI Holiday Recap!

FabCon Atlanta 2026 carousel

FabCon Atlanta 2026

Join us at FabCon Atlanta, March 16-20, for the ultimate Fabric, Power BI, AI and SQL community-led event. Save $200 with code FABCOMM.