calender table

when I'm trying to create a calendar table calender = calendar (MIN(project [contract start date],(MAX(project [contractenddate])..it is showing contract end date has some blank values,unable to crea...
  • v-eachen-msft's avatar
    6 years ago

    Hi Anonymous ,

     

    After my tests, blank values will not affect the result. You could check if your data used text type.

    And you could add filter to ignore blank values.

    calender =
    CALENDAR (
        MIN ( project[contract start date] ),
        CALCULATE (
            MAX ( project[contractenddate] ),
            FILTER ( project, project[contractenddate] <> BLANK () )
        )
    )