Skip to main content
cancel
Showing results for 
Search instead for 
Did you mean: 

The Power BI Data Visualization World Championships is back! Get ahead of the game and start preparing now! Learn more

Reply
Mike_Mace
Resolver I
Resolver I

Week difference with IFs

Happy lockdowning Forum,

 

I have a matrix with info:

1. A list of 25 deliverables with random plan dates and random dates they were submitted - these are sourced from two separate spreadsheets connected with a relationship

2. I created (head) columns by "starting-date" week. All random dates are grouped in those weeks

3. To calculate the delay in weeks I used a few variants of the following (which did not get me far)

week diff = DATEDIFF('Date Calendar'[Week start], TODAY(), WEEK) / 7

 

If "sub sum" is not 1, then the calculation in weeks should be

a. plan date upto current week

or

b. plan date upto week when "sub sum" = 1

Snip shows a good example

 
 
Snip:
 
 
Capture.JPG

2 REPLIES 2
Mike_Mace
Resolver I
Resolver I

Hi @Anonymous ,

 

This looks like a start to get there.

Making some comments and attaching a snip to back them up (green comments shows answer I'm aiming for)

 

Rows i/ii: these were submitted on the week they were planned for so i wouldnt expect to see a number showing delays under "week diff" in the following weeks. (in case I confused you, "week diff" should show the delay in weeks from the initial planned date)

Row iii: first week was missed so number 1 is correct. this was submitted on the second week so the number 1 should stop at second week. 3rd week i wouldnt expect to see anything as document iii is completed at week 2

Row iv: this looks like ought to be the other way around, 1st week missed so 1 week delay, 2nd week missed, 2 weeks delay, delivered on 3rd week measure should show 2 
Rows v/viii/x: as per (iv) numbers seem to be other way around

Rows vi until last, of which deliverables are expected on 2nd week onwards, they show a delay measure in "week diff" under weeks before they were actually planned. I would excpect to see a delay measure once a deliverable misses its planned week.

 

From what I see on your model, I wouldn't be able to progress this on my own! Thanks!

Snip:

comments on respond.png

Anonymous
Not applicable

Hi @Mike_Mace ,

I have updated your sample pbix file, please check whether that is what you want.

Week difference with IFs.JPG

Best Regards

 

Helpful resources

Announcements
Power BI DataViz World Championships

Power BI Dataviz World Championships

The Power BI Data Visualization World Championships is back! Get ahead of the game and start preparing now!

December 2025 Power BI Update Carousel

Power BI Monthly Update - December 2025

Check out the December 2025 Power BI Holiday Recap!

FabCon Atlanta 2026 carousel

FabCon Atlanta 2026

Join us at FabCon Atlanta, March 16-20, for the ultimate Fabric, Power BI, AI and SQL community-led event. Save $200 with code FABCOMM.

Top Solution Authors