Hi Guys, Having a mare with this one and just cannot get to work. I have a table of data where each project has allocated budget value. this in turn will be used between two dates (10-12-2018...
- 5 years ago
Ashish_Mathur
5 years agoSuper User
Hi,
How did you arrive at the figures in the last table of your original post. Between 10/12/2018 and 31/3/2023, there are 1,573 days. Between 10/12/2018 and 31/12/2018, there are 22 days. The proportionate agreement value to be booked in 2018 should be 14,102,475/1,573*22 = 197,237.41. How did you arrive at 271,201.44 for 2018?