Project Dates

Hello! I am trying to create a table in Power BI which will show time elapsed and time remaining in a project.

 

There's a few things I am trying to do:

I have the project contract start date and the end date but how do I populate a column to update with today's date?

Then I am guessing I will need a measure to calculate months remaining (end date - today date) and time elapsed with (today's date - start date)

 

Any help will be greatly appreciated!

1 ACCEPTED SOLUTION
Anonymous
Not applicable

Hi @livjay97 ,

I have created a simple sample, please refer to my pbix file to see if it helps you.

Create measures.

vpollymsft_0-1678686146463.png

 

There are different in all and Measure. You can choose the right measure according to your data.

 

If it does not help, please provide more details with your desired output and pbix file without privacy information (or some sample data) .

 

Best Regards
Community Support Team _ Polly

If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.

View solution in original post

1 REPLY 1
Anonymous
Not applicable

Hi @livjay97 ,

I have created a simple sample, please refer to my pbix file to see if it helps you.

Create measures.

vpollymsft_0-1678686146463.png

 

There are different in all and Measure. You can choose the right measure according to your data.

 

If it does not help, please provide more details with your desired output and pbix file without privacy information (or some sample data) .

 

Best Regards
Community Support Team _ Polly

If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.

Helpful resources

Announcements
November Power BI Update Carousel

Power BI Monthly Update - November 2025

Check out the November 2025 Power BI update to learn about new features.

Fabric Data Days Carousel

Fabric Data Days

Advance your Data & AI career with 50 days of live learning, contests, hands-on challenges, study groups & certifications and more!

FabCon Atlanta 2026 carousel

FabCon Atlanta 2026

Join us at FabCon Atlanta, March 16-20, for the ultimate Fabric, Power BI, AI and SQL community-led event. Save $200 with code FABCOMM.

Top Solution Authors