Power Query Duration between Dates excluding Weekends Wont Load
- 1 year ago
Hi Austen229022,
I have reproduced your scenario in Power BI as per your requirements. Please find attached
.pbixfile for your reference.If this response helps, consider marking it as “Accept as solution” and giving a “kudos” to assist other community members.
Thank you.
Hi Austen229022,
Instead of doing the step in Power Query, can you try doing with DAX?
Step-1: Create a Date table with excluding weekends and holidays
Step-2: Use the above Date table to join with your table
Best regards,
Maruthi
How can you do this with DAX?
- v-priyankata1 year agoCommunity Support
Hi Austen229022,
I have reproduced your scenario in Power BI as per your requirements. Please find attached
.pbixfile for your reference.If this response helps, consider marking it as “Accept as solution” and giving a “kudos” to assist other community members.
Thank you.- v-priyankata1 year agoCommunity Support
Hi Austen229022
May I ask if you have resolved this issue? If so, please mark the helpful reply and accept it as the solution. This will be helpful for other community members who have similar problems to solve it faster.
Thank you