I am creating a dashboard to monitoring all actitives that the team worked. I have a share point list that contain date and activity will performed during the year. 

So I need create a percentage indicator visual to show the total activities was done during a day. For example, today is 03/24/23 and I have 10 activities planned to perform however I only finished 5 activities therefore I conclused 50% of my planned activities.

How can I count the number of activities I need perform per day ? After count it I imagine that is possible create a percentage indicator.

  • Anonymous's avatar
    Anonymous
    3 years ago

    Hi Viniciussouza ,

     

    According to your description, here are my steps you can follow as a solution.

    (1) This is my test data.  

    (2) We can create three measures. 

    total activity = COUNTROWS(FILTER(ALL('Table'),'Table'[date]=MAX('Table'[date])))
    finished = CALCULATE(COUNTA('Table'[finished activity]),'Table'[finished activity]<>BLANK() && 'Table'[date]=MAX('Table'[date]))
    percentage = DIVIDE('Table'[finished],'Table'[total activity],0)

    (3) Then the result is as follows.

     

     

    If the above one can't help you get the desired result, please provide some sample data in your tables (exclude sensitive data) with Text format and your expected result with backend logic and special examples. It is better if you can share a simplified pbix file. Thank you.

     

    Best Regards,

    Neeko Tang

    If this post  helps, then please consider Accept it as the solution  to help the other members find it more quickly. 

2 Replies

  • Anonymous's avatar
    Anonymous
    Not applicable

    Hi Viniciussouza ,

     

    According to your description, here are my steps you can follow as a solution.

    (1) This is my test data.  

    (2) We can create three measures. 

    total activity = COUNTROWS(FILTER(ALL('Table'),'Table'[date]=MAX('Table'[date])))
    finished = CALCULATE(COUNTA('Table'[finished activity]),'Table'[finished activity]<>BLANK() && 'Table'[date]=MAX('Table'[date]))
    percentage = DIVIDE('Table'[finished],'Table'[total activity],0)

    (3) Then the result is as follows.

     

     

    If the above one can't help you get the desired result, please provide some sample data in your tables (exclude sensitive data) with Text format and your expected result with backend logic and special examples. It is better if you can share a simplified pbix file. Thank you.

     

    Best Regards,

    Neeko Tang

    If this post  helps, then please consider Accept it as the solution  to help the other members find it more quickly. 

    • Viniciussouza's avatar
      Viniciussouza
      Frequent Visitor

      Hello Anonymous ,

       

      Thanks for your reply. I tried to apply it in my dashboard although it'snt work well. I don´t know how add my .pbix here so I am sharing the print screen.

       

      Fifth column is activity date started

      Sixth column is activity date planed

      Seventh column is activity date finished

      So if the start date and finish date <= plan date the result was 1, whether start date and/or finish date > plan date result was 0. 

      In this case the percentual total was 37,5 %