MAQ gantt visual group task

Hi MAQ    In my example. the Project 1 is  divided in two phases Project ID Feha Inicio Fecha Fin Project 1 1 31/01/2019 10/02/2019 Project 1 2 01/03/2019 21/03/2019 Project 2...
  • Anonymous's avatar
    Anonymous
    7 years ago

    Hi Anonymous ,

    Nope, this visual not support this. If you have multiple category records, it will show as multiple line on visual instead of group them to one category.

    Regards,

    Xiaoxin Sheng

  • MAQSupport's avatar
    7 years ago

    Hello Anonymous ,

     

    The current version of Gantt Chart by MAQ Software does not support showing multiple bars in a row.

    We have added your request to our backlog.

     

    We will notify you on this thread when we enhance the visual with this feature.

     