Hi All,
I have created a burn down chart which i took from custom market place.
I have created planned hours for that, and will be comparing with actual hours to complete it.

Porvided below the formula for Planned hours to complete.
Planned Hours =
Var SprintStartDate = CALCULATE(FIRSTDATE('Calendar'[Date]),ALLSELECTED(Sheet1))
Var DaysSinceStart = DATEDIFF(SprintStartDate,Max('Calendar'[Date]),DAY)
Var BeginningStart = CALCULATE(MAX(Sheet1[Remaining Hours to complete]),ALLSELECTED(Sheet1))
Var SprintLength = 9
Return
IF(MAX('Calendar'[Date])>= SprintStartDate && MAX('Calendar'[Date])<= SprintStartDate+SprintLength,
BeginningStart - DaysSinceStart * (BeginningStart/SprintLength),BLANK())
Now my concern is how to exclude the weekend date in this formula i.e., i have to exclude saturday and sunday, because generally we won't work in weekend.
Once we removed then the Planned hours should be a straight line.
Please help me on this. Thank in advance.
Regards,
Prakash M