Gantt Chart with Measure
PowerBI Newbie here. With an Excel table as by datasource, I would like to build a Gantt chart that aggregates Task Category then shows the minimum Start Date and a Duration that is the difference between the minimum Start Date and the maximum End Date of all the Tasks that have the Task Category. I set up a Measure to calculate the minimum Start Date, but the Power BI Gantt Chart won't allow me to use it as the Start Date. The DAX for the measure (named "Start") is "Start = DATEVALUE(MIN(Tasks[In-Home]))". What am I doing wrong?
2 Replies
- Seward12533
Solution Sage
Measures have to be with aggregate calculations. Datevalue (if it’s even a Dax function) is a discrete calculation. Should just simply be
"Start = MIN(Tasks[In-Home]) // assumes Tasks[In-Home] is a date.- v-huizhn-msft
Microsoft Employee
Hi Seward12533,
Due to the nature of Gantt Chart, a start date for each task is essential. So we can not use a measure in a start-date level, we must put a column there. It's a truth after test. Please rethink your sample data and feature of Gantt Chart.
Best Regards,
Angelia