Hi sprasad ,
The dates are good. Please refer to the snapshot below.
Does it mean an Epics has many releases? Maybe you should consider the Epics as the parent task. Please also try the Gantt Chart released by MS.
Best Regards,
- sprasad7 years agoHelper II
Dale,
Release is a parent item and then Epic as child and then Feature as the sub child.
Let us take this scenarion: From the table Release ID - 42368 is spanning from 01-01-19 TO 28-02-19, but one of the Feature (4) in row4 is spanning from 15-02-19 TO 31-03-19. Now in the Gantt chart the Release dates gets extended as 01-01-19 TO 31-03-19, I am expecting that the Release will maintain its original duration i.e from 01-01-19 TO 28-02-19
I also tried the Gantt Chart from Microsoft, but the problem there is it shows the bars only for last child items which is Feature in my case. It should show the bars for Release and Epic as wel.
Regards