Finish date variance

Hi

 

I'm very, very new to Power BI......

 

I've prepared a report in table format linked to data from MS Project Online.

 

 I need to include a column that sets out how many days overdue a task is compared to its planned finish date is. I can see how to show the variance between a finish date and a baseline finish date, however that isn't what I'd need.

 

Thanks

 

 

2 ACCEPTED SOLUTIONS

Hi,

 

Try this calculated column formula

 

=[Planned Finsh Date]-TODAY()

 

Hope this helps.


Regards,
Ashish Mathur
http://www.ashishmathur.com
https://www.linkedin.com/in/excelenthusiasts/

View solution in original post

Hi @KeriHHBB

Please try this formula

Column = DATEDIFF([planned finish date],TODAY(),DAY)

This formula would calculate [the planned finish date]- today's date, thus you know how many days the task delays.

 

Best Regards

Maggie

View solution in original post

5 REPLIES 5
Ashish_Mathur
Super User
Super User

Hi,

 

Try this calculated column formula

 

=MAX([Planned FInish Date],[Actual FInish Date])-MIN([Planned FInish Date],[Actual FInish Date])

 

Hope this helps.


Regards,
Ashish Mathur
http://www.ashishmathur.com
https://www.linkedin.com/in/excelenthusiasts/
v-juanli-msft
Community Support
Community Support

Hi @KeriHHBB

Assume your table is like

1.png

Create a calculated columns in "Modeling"->New columns

Column = DATEDIFF([planned finish date],[actual finish date],DAY)

 

Best Regards

Maggie

Hi

Thanks for your responses.

In fact I want to compare the planned finish date against today's date so that I can see which tasks are late, and by how many days.

 

Hi @KeriHHBB

Please try this formula

Column = DATEDIFF([planned finish date],TODAY(),DAY)

This formula would calculate [the planned finish date]- today's date, thus you know how many days the task delays.

 

Best Regards

Maggie

Hi,

 

Try this calculated column formula

 

=[Planned Finsh Date]-TODAY()

 

Hope this helps.


Regards,
Ashish Mathur
http://www.ashishmathur.com
https://www.linkedin.com/in/excelenthusiasts/

Helpful resources

Announcements
LearnSurvey

Fabric certifications survey

Certification feedback opportunity for the community.

PBI_APRIL_CAROUSEL1

Power BI Monthly Update - April 2024

Check out the April 2024 Power BI update to learn about new features.

April Fabric Community Update

Fabric Community Update - April 2024

Find out what's new and trending in the Fabric Community.