Hi all, I have a form that I am trying to graph in Power BI.  The form contains a start date field (Date Selector) and a numerical entry field called Amortization for the duration and I would like to calculate an end date (months) based on that number. My issue is that I cannot figure out how to get DATEADD to accept the values from the Amortization field.

 

Any help would be appreciated

  • Hey MarcMendez ,

     

    I do not fully understand the structure of the table "", but you can use the below DAX to create a calculated column:

    Amortization End Date = 
    DATEADD( 'AOP'[Project Start Date] , 'AOP'[Hardware Amortization (Months)] , MONTH )

    Based on the sample data the following screenshot shows the result:

     

    Hopefully, this helps to tackle your challenge.

     

    Regards,

    Tom

     

5 Replies

  • Hey marcmen ,

     

    please provide a pbix that contains some sample data. Upload the pbix to onedrive or dropbox and share the link. Describe the expected result based on the sample data you provided.

     

    Regards,

    Tom

  • TomMartens  - thanks for the response. 

     

    The PBX can be found here Annual Operating Plan Dashboard Draft.pbix

    At this time, I am looking to be able to calculate an end date for the amortization fields. For example

    [Project Start Date] + [Hardware Amortization (Months)] = Amortization End Date. 

    [Hardware List Price] / [Hardware Amortization (Months)] = Monthly Cost 

     

     

    Once I have the end date, I plan on duplicating the process for each amortized category, hopefully allowing me to create year-end rollups and a schedule based on another article I have read.

    I appreciate your help

  • Hey MarcMendez ,

     

    I do not fully understand the structure of the table "", but you can use the below DAX to create a calculated column:

    Amortization End Date = 
    DATEADD( 'AOP'[Project Start Date] , 'AOP'[Hardware Amortization (Months)] , MONTH )

    Based on the sample data the following screenshot shows the result:

     

    Hopefully, this helps to tackle your challenge.

     

    Regards,

    Tom

     

    • marcmen's avatar
      marcmen
      Helper I

      TomMartens -thank you for this. You cannot understand the table structure because there is none 😁. This PBX is a brain dump at the moment  - I need to rebuild it. 

       

      • marcmen's avatar
        marcmen
        Helper I