Forum Discussion

Lsh0576's avatar
Lsh0576
Frequent Visitor
3 years ago
Solved

DAX Query Help Please!

Hello there! 

 

I would like to ask for help with writing a query in DAX. Here is what I am trying to do..

 

I will be reporting this Resource Capacity' equation on a weekly basis:

 

Number of Administrators (17) X Average Work Completed (12) = 204 multiply by fraction of weeks remaining in the year (XX / 52)

 

Can someone please help me write this? I got to the 204 part but not sure how to write the fraction of weeks remaining in the year.

 

Thank you so much, I appreciate the help!

 

Belle

  • Hi,

    Write this masure to calculated Remaining weeks in year

    Remaining weeks in year = calculate(min(Calendar[Weeks until end of year]),datesbetween(calendar[date],date(year(today()),12,31),date(year(today()),12,31)))-calculate(min(Calendar[Weeks until end of year]),datesbetween(calendar[date],today(),today()))+1

    Use this measure in the denominator.

4 Replies

  • Hi,

    Ensure that you have a Calendar Table with a week number column in your PBI file.  Share the download link of the PBI file.

    • Lsh0576's avatar
      Lsh0576
      Frequent Visitor

      Hello there! So I got the calendar table built with a column of 'weeks remaining in the year':

      Now I need to know how to incorporate this to build the metric:

       

      Instead of dividing by 2, I need to multiply by fraction of weeks remaining in the year.

      • Ashish_Mathur's avatar
        Ashish_Mathur
        Super User

        Hi,

        Write this masure to calculated Remaining weeks in year

        Remaining weeks in year = calculate(min(Calendar[Weeks until end of year]),datesbetween(calendar[date],date(year(today()),12,31),date(year(today()),12,31)))-calculate(min(Calendar[Weeks until end of year]),datesbetween(calendar[date],today(),today()))+1

        Use this measure in the denominator.

  • Lsh0576's avatar
    Lsh0576
    Frequent Visitor

    I also created a date field in my master table ('Date_Today') so I can link the Master table to the Calendar table by DATE field.