Cumulative Totals Not Working Correctly
I'm seeing some odd behavior when trying to calculate the cumulative totals of activities completed in a project schedule. I have two relationships between the data table and the date table, an acti...
v-xicai
Community Support
7 years agoHi Anonymous ,
Have you used" SUMX(AP,[As-Built Activity Count] " in measures, please add and try it again.
Best Regards,
Amy
If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.
Anonymous
7 years agoNot applicable
Hi Amy,
Right now I'm using this:
AP Cumulative Qty = CALCULATE(SUMX(AP,[As-Planned Activity Count]),FILTER(ALLSELECTED('Date Table'[Date]),'Date Table'[Date] <= MAX('Date Table'[Date])))
and
AB Cumulative Qty = CALCULATE(SUMX(AP,[As-Built Activity Count]),USERELATIONSHIP(AP[AB Finish],'Date Table'[Date]),FILTER(ALLSELECTED('Date Table'[Date]),'Date Table'[Date] <= MAX('Date Table'[Date])))
This still results in a weird result as shown above (that set of unexpected 8's in the AP Cumulative Qty and the incorrect totals in the AB Cumulative Qty.