Create a Work Resource Visual

Hello, I am trying to create a visual that will show the weekly workload for staff resources across time for a planning tool. 

 

This is the information I have below: Each staff member is assigned to a project size that requires a different level of hours per week of the project and projects are planned for the year. 

 

Project IDStaff ResourceProject Size       Planned StartPlanned End
1ASmall2022-04-032022-04-17
2AMedium2022-04-102022-05-08
3BMedium2022-04-032022-05-01
4BMedium2022-04-242022-05-22
5BLarge2022-05-012022-07-10
6CLarge2022-04-032022-06-12
7CLarge2022-04-242022-07-03
8CMedium2022-05-152022-06-12

 

  Hours Required Per Week
Project SizeNumber of WeeksWeek 1Week 2Week 3Week 4Week 5Week 6Week 7Week 8Week 9Week 10
Small273        
Medium 45523      
Large105322112342

 

 

Ultimately I want to create a visual with the week number on the x axis and the number of hours required on the y with the staff resource as the values like this

Pic 2.JPG

 

I am struggling to create a measure that will account for the variable time required for each project during the week it runs and then sum it up for the staff resource by the week. Any help or insights on how to do this would be greatly appreciated!

1 ACCEPTED SOLUTION
amitchandak
Super User
Super User

@Anonymous , See Matrix as Project plan

A matrix as Project plan Visual: https://youtu.be/R25QoiyoSVs

 

Check

https://community.powerbi.com/t5/Community-Blog/How-to-divide-distribute-values-between-start-date-or-end-date/ba-p/1503785

Share with Power BI Enthusiasts: Full Power BI Video (20 Hours) YouTube
Microsoft Fabric Series 60+ Videos YouTube
Microsoft Fabric Hindi End to End YouTube

View solution in original post

2 REPLIES 2
Anonymous
Not applicable

Thank you, this worked great!

amitchandak
Super User
Super User

@Anonymous , See Matrix as Project plan

A matrix as Project plan Visual: https://youtu.be/R25QoiyoSVs

 

Check

https://community.powerbi.com/t5/Community-Blog/How-to-divide-distribute-values-between-start-date-or-end-date/ba-p/1503785

Share with Power BI Enthusiasts: Full Power BI Video (20 Hours) YouTube
Microsoft Fabric Series 60+ Videos YouTube
Microsoft Fabric Hindi End to End YouTube

Helpful resources

Announcements
Power BI DataViz World Championships

Power BI Dataviz World Championships

The Power BI Data Visualization World Championships is back! Get ahead of the game and start preparing now!

December 2025 Power BI Update Carousel

Power BI Monthly Update - December 2025

Check out the December 2025 Power BI Holiday Recap!

FabCon Atlanta 2026 carousel

FabCon Atlanta 2026

Join us at FabCon Atlanta, March 16-20, for the ultimate Fabric, Power BI, AI and SQL community-led event. Save $200 with code FABCOMM.