Forum Discussion
Anonymous
7 years agoNot applicable
Counting workdays...
I have the master calendar all set with holidays flagged. I created WorkDay =1 or 0 to indicate if its a workday or not (sat, sun and holidays = 0). CALCULATE(SUM(mastercalendar[WorkDay]),DAT...
- Anonymous6 years ago
Crossing my fingers. Seems to work (the missing piece of the equation)
WorkdaysBetween =CALCULATE(SUM(mastercalendar[IsWorkday]),ALL(mastercalendar),DATESBETWEEN(mastercalendar[full_date],requests[requestdate],requests[completedate]))In case you're interested, in power queryTable.AddColumn(#"DayOfWeek", each Date.DayOfWeek([full_date]))Table.AddColumn(#"IsWeekday", each if [DayOfWeek]=0 or [DayOfWeek]=6 then 0 else 1)Table.AddColumn(#"IsWeekend", each 1- [IsWeekday])Table.AddColumn(#"IsHoliday", each if [Holiday]="" then 0 else 1)##holidays were built using Date patternsTable.AddColumn(#"IsWorkday", each if [IsWeekend]+[IsHoliday]>0 then 0 else 1)
Ashish_Mathur
7 years agoSuper User
Hi,
I do not see a mistake there. Share the link from where i can download your PBI file.