Hundoa
Frequent Visitor

Count of working days between two date columns, excluding holidays

Hello,

 

I've looked at a number of posts on similar issues, however I still can't get this to work. 

 

I have a table with work received and closed dates in separate columns. I need to calculate the number of working days between the two dates, excluding and holidays. 

 

1.PNG

 

I have a date table set up, which pulls through the holidays from another table and a column which gives a 1 or 0, depending on whether it is a working day or not, using the following logic

 

Duration 1/0 = IF(OR('Date Table'[Day of Week]=5,'Date Table'[Day of Week]=6),0,IF('Date Table'[Is Bank Holiday]="",1,0))

 

2.PNG 

Using DATEDIFF, I can get the number of days between the two date field, however I'm getting stuck on how to filter out the holidays on the date table. 

 3.PNG

 

Days between Rec/Closed = DATEDIFF('Workflow Duration'[Received Date],'Workflow Duration'[Closed Date],DAY)+1

 

Could someone please let me know what I should be doing with the logic to achieve this?

 

Thank you. 

 

 

1 ACCEPTED SOLUTION
amitchandak
Super User
Super User

@Hundoa , refer two the second page - workday diff of the attached file after signature

Or Refer :https://www.sqlbi.com/articles/counting-working-days-in-dax/

Join us as experts from around the world come together to shape the future of data and AI!
At the Microsoft Analytics Community Conference, global leaders and influential voices are stepping up to share their knowledge and help you master the latest in Microsoft Fabric, Copilot, and Purview.
️ November 12th-14th, 2024
 Online Event
Register Here

View solution in original post

2 REPLIES 2
V-pazhen-msft
Community Support
Community Support

@Hundoa 

Check my example below, pbix also attached. You may add other bank holiday conditions to the filter if you have.

Column = CALCULATE(COUNTROWS('Date table'),
                FILTER('Date table',[Date]>=EARLIER(([Start]))&&[Date]<=EARLIER([Close])),
                FILTER('Date table',WEEKDAY('Date table'[Date],2)<>6 &&WEEKDAY('Date table'[Date],2)<>7))

 working days in range.JPG


Paul Zheng _ Community Support Team
If this post helps, please Accept it as the solution to help the other members find it more quickly.

amitchandak
Super User
Super User

@Hundoa , refer two the second page - workday diff of the attached file after signature

Or Refer :https://www.sqlbi.com/articles/counting-working-days-in-dax/

Join us as experts from around the world come together to shape the future of data and AI!
At the Microsoft Analytics Community Conference, global leaders and influential voices are stepping up to share their knowledge and help you master the latest in Microsoft Fabric, Copilot, and Purview.
️ November 12th-14th, 2024
 Online Event
Register Here

Helpful resources

Announcements
November Carousel

Fabric Community Update - November 2024

Find out what's new and trending in the Fabric Community.

Live Sessions with Fabric DB

Be one of the first to start using Fabric Databases

Starting December 3, join live sessions with database experts and the Fabric product team to learn just how easy it is to get started.

Las Vegas 2025

Join us at the Microsoft Fabric Community Conference

March 31 - April 2, 2025, in Las Vegas, Nevada. Use code MSCUST for a $150 discount! Early Bird pricing ends December 9th.

Nov PBI Update Carousel

Power BI Monthly Update - November 2024

Check out the November 2024 Power BI update to learn about new features.