SaurabhGupta
Frequent Visitor

Change in column's data on the basis of slicer

Hi,

 

Is it possible to create a column which has dynamic data based upon the slicer? For example,

A project has a start date and an end date. I will have a slicer in whcih I will specify a range of dates. Then, my column will give me the number of days that project has in the selected range of dates.

1 ACCEPTED SOLUTION

Hi @SaurabhGupta,

 

Try this formula please.

Measure =
VAR minDate =
    MIN ( 'calendar'[date] )
VAR maxDate =
    MAX ( 'calendar'[date] )
VAR startDate =
    MIN ( project[start date] )
VAR endDate =
    MIN ( project[end date] )
RETURN
    SWITCH (
        TRUE (),
        startDate < minDate
            && endDate < minDate, 0,
        startDate > maxDate
            && endDate > maxDate, 0,
        startDate < minDate
            && endDate > maxDate, DATEDIFF ( minDate, maxDate, DAY ),
        startDate < minDate
            && endDate > minDate
            && endDate < maxDate, DATEDIFF ( minDate, endDate, DAY ),
        endDate > minDate
            && endDate < maxDate
            && startDate > minDate
            && startDate < maxDate, DATEDIFF ( startDate, endDate, DAY ),
        endDate > maxDate
            && startDate > minDate
            && startDate < maxDate, DATEDIFF ( startDate, maxDate, DAY )
    )

Best Regards,

Dale

Community Support Team _ Dale
If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.

View solution in original post

3 REPLIES 3
Anonymous
Not applicable

Yes,if your data model has the supporting data, this is possble.

 

Thanks

Raj

Thanks Raj,

Could you please tell me how to do that?

I have Project start date, project end date, and a calendar table (that will be used in a slicer for selecting the range of dates).

How can I create a new column in my project table which will show the number of days that a project has in the selected range of dates?

Hi @SaurabhGupta,

 

Try this formula please.

Measure =
VAR minDate =
    MIN ( 'calendar'[date] )
VAR maxDate =
    MAX ( 'calendar'[date] )
VAR startDate =
    MIN ( project[start date] )
VAR endDate =
    MIN ( project[end date] )
RETURN
    SWITCH (
        TRUE (),
        startDate < minDate
            && endDate < minDate, 0,
        startDate > maxDate
            && endDate > maxDate, 0,
        startDate < minDate
            && endDate > maxDate, DATEDIFF ( minDate, maxDate, DAY ),
        startDate < minDate
            && endDate > minDate
            && endDate < maxDate, DATEDIFF ( minDate, endDate, DAY ),
        endDate > minDate
            && endDate < maxDate
            && startDate > minDate
            && startDate < maxDate, DATEDIFF ( startDate, endDate, DAY ),
        endDate > maxDate
            && startDate > minDate
            && startDate < maxDate, DATEDIFF ( startDate, maxDate, DAY )
    )

Best Regards,

Dale

Community Support Team _ Dale
If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.

Helpful resources

Announcements
Las Vegas 2025

Join us at the Microsoft Fabric Community Conference

March 31 - April 2, 2025, in Las Vegas, Nevada. Use code MSCUST for a $150 discount!

Dec Fabric Community Survey

We want your feedback!

Your insights matter. That’s why we created a quick survey to learn about your experience finding answers to technical questions.

ArunFabCon

Microsoft Fabric Community Conference 2025

Arun Ulag shares exciting details about the Microsoft Fabric Conference 2025, which will be held in Las Vegas, NV.

December 2024

A Year in Review - December 2024

Find out what content was popular in the Fabric community during 2024.