Hi,

 

I am trying to create a measure formula that calculates the % change year over year that also takes into account changes from negative to positive numbers. I have the formula written out in excel below, but when I try to get the same formula written in PBI I get an error saying too few arguments passed. Any help would be greatly appreciated. 

 

Excel Formula

=IF(LY %=0,0,(IF(LY %<0,(( LY % - TY %)/ LY %)*100,(( LY % - TY %)/ LY %)*-100)))

 

PBI Measure

% Change Calculated = IF([LY Shortage Rate Calculated]=0,0,IF([LY Shortage Rate Calculated]>0,([LY Shortage Rate Calculated]-[TY Shortage Rate Calculated]/[LY Shortage Rate Calculated])*-1,IF([LY Shortage Rate Calculated]-[TY Shortage Rate Calculated]/[LY Shortage Rate Calculated])))
2 ACCEPTED SOLUTIONS
dedelman_clng
Community Champion
Community Champion

You have an extra IF towards the end.  Should be

 

% Change Calculated =
IF (
    [LY Shortage Rate Calculated] = 0,
    0,
    IF (
        [LY Shortage Rate Calculated] > 0,
        ( [LY Shortage Rate Calculated]
            - [TY Shortage Rate Calculated] / [LY Shortage Rate Calculated] )
            * -1,
        ( [LY Shortage Rate Calculated]  ##You had an extra IF here
            - [TY Shortage Rate Calculated] / [LY Shortage Rate Calculated] )
    )
)

View solution in original post

Thanks for the quick reply Dedelman_clng! I added in some divides into the formula with your change and it worked perfectly. 

 

% Change Calculated =
IF (
    [LY Shortage Rate Calculated] = 0,
    0,
    IF (
        [LY Shortage Rate Calculated] > 0,
       **DIVIDE** ( [LY Shortage Rate Calculated]
            - [TY Shortage Rate Calculated] , [LY Shortage Rate Calculated] )
            * -1,
        **DIVIDE**( [LY Shortage Rate Calculated] - [TY Shortage Rate Calculated] , [LY Shortage Rate Calculated] )
    )
)

View solution in original post

2 REPLIES 2
dedelman_clng
Community Champion
Community Champion

You have an extra IF towards the end.  Should be

 

% Change Calculated =
IF (
    [LY Shortage Rate Calculated] = 0,
    0,
    IF (
        [LY Shortage Rate Calculated] > 0,
        ( [LY Shortage Rate Calculated]
            - [TY Shortage Rate Calculated] / [LY Shortage Rate Calculated] )
            * -1,
        ( [LY Shortage Rate Calculated]  ##You had an extra IF here
            - [TY Shortage Rate Calculated] / [LY Shortage Rate Calculated] )
    )
)

Thanks for the quick reply Dedelman_clng! I added in some divides into the formula with your change and it worked perfectly. 

 

% Change Calculated =
IF (
    [LY Shortage Rate Calculated] = 0,
    0,
    IF (
        [LY Shortage Rate Calculated] > 0,
       **DIVIDE** ( [LY Shortage Rate Calculated]
            - [TY Shortage Rate Calculated] , [LY Shortage Rate Calculated] )
            * -1,
        **DIVIDE**( [LY Shortage Rate Calculated] - [TY Shortage Rate Calculated] , [LY Shortage Rate Calculated] )
    )
)

Helpful resources

Announcements
New to Fabric survey Carousel

New to Fabric Survey

If you have recently started exploring Fabric, we'd love to hear how it's going. Your feedback can help with product improvements.

Power BI DataViz World Championships carousel

Power BI DataViz World Championships - June 2026

A new Power BI DataViz World Championship is coming this June! Don't miss out on submitting your entry.

Join our Fabric User Panel

Join our Fabric User Panel

Share feedback directly with Fabric product managers, participate in targeted research studies and influence the Fabric roadmap.

March Power BI Update Carousel

Power BI Community Update - March 2026

Check out the March 2026 Power BI update to learn about new features.

Users online (3,916)