Hello, Can anyone help me with one of the thing I am trying to do.
I am trying to find the Average allocation % for a resource and I need that to calculate for a selected date range. I wrote a dax
Total Resource Allocation = AVERAGEX ( VALUES('Resource Allocation Forecast'[Resource NameId]),CALCULATE(AVERAGE('Resource Allocation Forecast'[Allocation %])))
for calculating the average and I am not getting the result I need.
Example below.
Allocated projects for a resource in each montth
Sum of allocated hours in each month for a Resource
I want to calculate average allocated hours from sep to dec . "85+80+80+35/4".
Appriciate your help on this.
Thank you
Hi,
Try this measure
=AVERAGEX(SUMMARIZE(VALUES(Calendar[Month]),[Month],"ABCD",SUM('Resource Allocation Forecast'[Allocation %])),[ABCD])
Drag this measure to a card visual. In the slicer/filter, select a particular resource and year. Ensure that the Year is dragged from the Calendar Table. There should be a relationship from the Date column of the Resource Allocation Forecast table to the Date column of the Calendar Table.
Thank you for helping me .
I tried the dax but, this giving me a in correnct average value
Card Value
Average = AVERAGEX(SUMMARIZE(VALUES('Date'[Calendar Month Name]),[Calendar Month Name],"ABCD",SUM('Resource Allocation Forecast'[Allocation %])),[ABCD])
How can we sum the distinct values ? I hvae multiple entries for a single resouce accoriding to their start and end date.
Below is the DAX which I am using for calculating the total of project hours for emplyess in every month/week. incase if this helps to understand better.
Total Allocation = SUMX(DISTINCT('Resource Allocation Forecast'[ProjectId]),CALCULATE(AVERAGE('Resource Allocation Forecast'[Allocation %])))
Thanks,
Apaco
Hi,
Describe your question in detail. Share the link from where i can download your PBI file and show the expected result.
Hello,
Below is a snapshot of my table structure. In my graph i am dispaying the weekly sum allocation for each project and in the other graph I am showing total allocation for each resource in month/week ( I have attached two graph snapshot in my question).
Table Snapshot
Now , I am trying to show the total average allocation percentage of a resource (all projects) in a selected date range.
If you see my graph in the questions, In september total allocation is 85 and in Oct & Nov, total allocation is 80, And in december it is 35. I need a score card which shows the average allocation of resource in 4 months. (85+80+80+35)/4
Please let me know if this helps.
Thanks
This is your chance to engage directly with the engineering team behind Fabric and Power BI. Share your experiences and shape the future.
Check out the June 2025 Power BI update to learn about new features.
User | Count |
---|---|
80 | |
76 | |
60 | |
36 | |
33 |
User | Count |
---|---|
91 | |
60 | |
59 | |
49 | |
45 |