Adjust timeline for Gannt Chart
I'd like to manually set the timeline date range, rather than it scaling based on the data displayed. For example, i'd like the Timeline to display Jan - Dec of 2019. As of right now, It stops at today's date in October and starts when the first task started in March. Is there a way to do this?
1 Reply
- dax
Community Support
Hi wewong18,
Based on my test, I find that time axis in Gantt chart is based on date in your table, you can't set custom time axis, this is by design. You could submit this requirement on Power BI Ideas.
Best Regards,
Zoe ZhiIf this post helps, then please consider Accept it as the solution to help the other members find it more quickly.