Adding only workdays to a specific date
- 8 years ago
Hi,
I created the calculations.
Try having a look at this: https://www.dropbox.com/s/5fareeag77bfc6x/power%20bi%20example.pbix?dl=0&m=
Result:
- 8 years ago
Okay - to assist others with similar challenges I will just make a short description of the solution I created.
First make sure that there is a relationship between the table and the calendar table.
Then in the calendar table create a few columns to create an index for workingdays
IsWorkday = SWITCH( WEEKDAY('Calendar'[Date]); 1; 0; 7; 0;1 ) WorkingDayIndex = RANKX( FILTER( 'Calendar'; 'Calendar'[IsWorkDay] = 1 ); 'Calendar'[Date]; ;ASC )Then in the table that should hold the result I created this calculation that make a simple lookup in the calendar table using the index column created above.
NewDate = VAR DateIdx = CALCULATE( MAX( 'Calendar'[WorkingDayIndex] ); 'Table1'[Date] = RELATED('Calendar'[Date] ) ) VAR NewDateIdx = DateIdx + Table1[Transport days] RETURN CALCULATE( MAX('Calendar'[Date]); FILTER( ALL('Calendar'); 'Calendar'[WorkingDayIndex] = NewDateIdx && 'Calendar'[IsWorkday] = 1 ) )
Sure thing
A couple of dates as an example. We need to add these days to the date, but make sure that only the work days gets added, skip saturday and sunday
As an example to further explane what i mean
the date 02.04.2017 with 16 days transport time would need the result to be 24.04.2017 when just counting work days.
and NOT 18.04.2017 (countet with weekends)
- sdjensen8 years agoSolution Sage
Try adding a working days index to your period table. If a day is not a working day then assign the same index number to this day as the previous day - then you should be able to calculate a column in your table where you find the index of your initial date add the transportation days to the index and return the lowest date with that index.
- Anonymous8 years agoNot applicable
thank you for the reply
Could you give me an example on how you would write that? i am still very new to writing my own columns/measures
- sdjensen8 years agoSolution Sage
This would be much easier if you shared a base model with some date - at least the data you posted earlier (as a picture) and a period table.
But to calculate the index in your period table you could try something like this.
Column1: IsWorkingDay = IF( Period[DayOfWeekNumber] = 6 || Period[DayOfWeekNumber] = 7; 0; 1 ) Column2: WorkingDaysIndex = RANKX( FILTER( Period; Period[IsWorkingDay] = 1 ); Period[Date]; ;ASC )IsWorkingDay calculates a column that will return a 1 if the day is not a Saturday or Sunday.
WorkingDaysIndex then calculates the index based on IsWorkingDay.
I can see from my small test that the rank on a Saturday is 1 larger than on a Friday, so instead of MIN date you should find the MAX date where index is equal Index from starting date + Transportation days