Add Conditional Tasks to Existing Schedules
v-lid-msft Thank you for the quick reply,
So far when I merge the tables with the settings you've shown and then expand the few columns I get null values for everything. I'm wondering if the fact that there other levels to the heirarchy is affecting the results.
For example:
Task 1 exists in North America, LATAM, and EMEA for the same project number. So within Project ABC123 there are multiple Start/Finish dates for Task 1 depending on the region. Does that impact how we would approach this?
The way I've added tasks manually in the past was to unpivot my task column, then add a new column with the specific task, populate with a formula referencing the other applicable task, then once again pivoting the data into a task column inclusive of my newly added column. This works...but for 150 columns it's a real pain...
Hi Anonymous ,
How about the result after you follow the suggestions mentioned in my original post?Could you please provide more details about it If it doesn't meet your requirement?
Best regards,
- Anonymous6 years agoNot applicable
I apologize for the delayed response. With all of the COVID-19 issues this task has temporarily taken a backseat at work. I truly appreciate your assistance and once I'm able to get back to this topic I will post a response on how your solution worked.