Join us at FabCon Atlanta from March 16 - 20, 2026, for the ultimate Fabric, Power BI, AI and SQL community-led event. Save $200 with code FABCOMM.
Register now!To celebrate FabCon Vienna, we are offering 50% off select exams. Ends October 3rd. Request your discount now.
I have the following table and I want to calculate how many tasks based on project phase over plan, initiate and go live. These are 3 seperate measures which will calculate count, the number of tasks by market (UK, DE, AUS etc) in business area (Strategic, Consumer, etc).
However, I want each measure when market = all then add the value to each market (UK, DE,AUS, etc) as I have a visual that is calculating the number of complete over the markets and I cannot have ALL market into my table visual, as I need to compare which markets have completed the most.
So when market equals all, add that value to each portfolio's value. For instance there are 2 tasks completed in the plan project stage for business strategic area , however, there are 3 DE tasks in plan in the same area so I want it it to show there has been 5 completed for DE for plan just for strategic, etc.
Market | Business Area | Projects | Phase | Status | Actual Date | Expected Date |
All | Analytics | Task1 | Plan | In Progress | 01/01/2022 | 01/01/2022 |
All | Analytics | Task2 | Initiate | In Progress | 02/01/2022 | 02/01/2022 |
All | Analytics | Task3 | Initiate | In Progress | 03/01/2022 | 03/01/2022 |
All | Analytics | Task4 | Plan | In Progress | 04/01/2022 | 04/01/2022 |
All | Analytics | Task5 | Plan | In Progress | 05/01/2022 | 05/01/2022 |
All | Analytics | Task6 | Plan | In Progress | 06/01/2022 | 06/01/2022 |
UK | Strategic | Task7 | Initiate | Not Started | 07/01/2022 | 07/01/2022 |
UK | Strategic | Task8 | Initiate | In Progress | 08/01/2022 | 08/01/2022 |
UK | Strategic | Task9 | Plan | In Progress | 09/01/2022 | 09/01/2022 |
UK | Strategic | Task10 | Go Live | Completed | 10/01/2022 | 10/01/2022 |
UK | Strategic | Task11 | Go Live | In Progress | 11/01/2022 | 11/01/2022 |
UK | Strategic | Task12 | Go Live | In Progress | 12/01/2022 | 12/01/2022 |
UK | Strategic | Task13 | Initiate | Completed | 13/01/2022 | 13/01/2022 |
DE | Strategic | Task14 | Initiate | Completed | 14/01/2022 | 14/01/2022 |
DE | Strategic | Task15 | Plan | Completed | 15/01/2022 | 15/01/2022 |
DE | Strategic | Task16 | Go Live | Completed | 16/01/2022 | 16/01/2022 |
DE | Strategic | Task17 | Go Live | Completed | 17/01/2022 | 17/01/2022 |
DE | Strategic | Task18 | Initiate | Completed | 18/01/2022 | 18/01/2022 |
DE | Strategic | Task19 | Initiate | Completed | 19/01/2022 | 19/01/2022 |
DE | Strategic | Task20 | Initiate | Completed | 20/01/2022 | 20/01/2022 |
DE | Strategic | Task21 | Go Live | In Progress | 21/01/2022 | 21/01/2022 |
DE | Strategic | Task22 | Go Live | In Progress | 22/01/2022 | 22/01/2022 |
All | Transformation | Task23 | Plan | Completed | 23/01/2022 | 23/01/2022 |
All | Transformation | Task24 | Go Live | Completed | 24/01/2022 | 24/01/2022 |
All | Transformation | Task25 | Initiate | Completed | 25/01/2022 | 25/01/2022 |
All | Transformation | Task26 | Initiate | Completed | 26/01/2022 | 26/01/2022 |
All | Transformation | Task27 | Plan | Completed | 27/01/2022 | 27/01/2022 |
All | Transformation | Task28 | Plan | Completed | 28/01/2022 | 28/01/2022 |
All | Transformation | Task29 | Go Live | In Progress | 29/01/2022 | 29/01/2022 |
All | Transformation | Task30 | Go Live | Completed | 30/01/2022 | 30/01/2022 |
All | Transformation | Task31 | Initiate | Completed | 31/01/2022 | 31/01/2022 |
USA | Strategic | Task32 | Plan | Completed | 01/02/2022 | 01/02/2022 |
USA | Strategic | Task33 | Initiate | Completed | 02/02/2022 | 02/02/2022 |
USA | Strategic | Task34 | Initiate | Completed | 03/02/2022 | 03/02/2022 |
USA | Strategic | Task35 | Go Live | Completed | 04/02/2022 | 04/02/2022 |
USA | Strategic | Task36 | Initiate | Completed | 05/02/2022 | 05/02/2022 |
USA | Strategic | Task37 | Go Live | Completed | 06/02/2022 | 06/02/2022 |
USA | Strategic | Task38 | Go Live | Completed | 07/02/2022 | 07/02/2022 |
USA | Strategic | Task39 | Initiate | Not Started | 08/02/2022 | 08/02/2022 |
USA | Strategic | Task40 | Go Live | Completed | 09/02/2022 | 09/02/2022 |
All | Pharma | Task41 | Plan | Completed | 10/02/2022 | 10/02/2022 |
All | Pharma | Task42 | Plan | Completed | 11/02/2022 | 11/02/2022 |
All | Pharma | Task43 | Plan | Completed | 12/02/2022 | 12/02/2022 |
All | Pharma | Task44 | Plan | Completed | 13/02/2022 | 13/02/2022 |
All | Pharma | Task45 | Initiate | Completed | 14/02/2022 | 14/02/2022 |
AUS | Strategic | Task46 | Initiate | Completed | 15/02/2022 | 15/02/2022 |
AUS | Strategic | Task47 | Plan | Completed | 16/02/2022 | 16/02/2022 |
AUS | Strategic | Task48 | Initiate | Completed | 17/02/2022 | 17/02/2022 |
AUS | Strategic | Task49 | Go Live | Not Started | 18/02/2022 | 18/02/2022 |
AUS | Strategic | Task50 | Go Live | Not Started | 19/02/2022 | 19/02/2022 |
AUS | Strategic | Task51 | Go Live | In Progress | 20/02/2022 | 20/02/2022 |
AUS | Strategic | Task52 | Go Live | In Progress | 21/02/2022 | 21/02/2022 |
All | Strategic | Task53 | Plan | Completed | 22/02/2022 | 22/02/2022 |
All | Strategic | Task54 | Initiate | Not Started | 23/02/2022 | 23/02/2022 |
All | Strategic | Task55 | Go Live | Not Started | 24/02/2022 | 24/02/2022 |
All | Strategic | Task56 | Initiate | Completed | 25/02/2022 | 25/02/2022 |
All | Strategic | Task57 | Go Live | Completed | 26/02/2022 | 26/02/2022 |
All | Consumer | Task58 | Plan | Completed | 27/02/2022 | 27/02/2022 |
All | Consumer | Task59 | Plan | Completed | 28/02/2022 | 28/02/2022 |
All | Consumer | Task60 | Plan | Completed | 01/03/2022 | 01/03/2022 |
All | Consumer | Task61 | Go Live | Completed | 02/03/2022 | 02/03/2022 |
All | Consumer | Task62 | Initiate | Completed | 03/03/2022 | 03/03/2022 |
All | Consumer | Task63 | Plan | Completed | 04/03/2022 | 04/03/2022 |
All | Consumer | Task64 | Initiate | Completed | 05/03/2022 | 05/03/2022 |
All | Consumer | Task65 | Initiate | Completed | 06/03/2022 | 06/03/2022 |
All | Consumer | Task66 | Initiate | Completed | 07/03/2022 | 07/03/2022 |
All | Strategic | Task67 | Plan | Completed | 08/03/2022 | 08/03/2022 |
All | Strategic | Task68 | Initiate | Completed | 09/03/2022 | 09/03/2022 |
You can try the following dax.
Create calculated table.
Table =
FILTER(
'Table','Table'[Market]="All"&&'Table'[Status]="Completed")
Create measure.
Flag =
var _countgroup=
COUNTX(
FILTER(ALL('Table'),'Table'[Market]=MAX('Table'[Market])&&
'Table'[Business Area ]=MAX('Table'[Business Area ])&&
'Table'[Phase]=MAX('Table'[Phase])&&'Table'[Status]=MAX('Table'[Status])),[Market])
var _counall=
COUNTX(
FILTER(ALL('Table 2'),
[Business Area ]=MAX('Table'[Business Area ])&&[Phase]=MAX('Table'[Phase])),[Market])
return
_counall+ _countgrou
Best Regards,
Liu Yang
If this post helps, then please consider Accept it as the solution to help the other members find it more quickly