Distributing values periodically between start and finish date

Hi Experts,

Can you please suggest me DAX measure to distribute the values in "target_qty" column periodically in days between "target_start_date" and "target_finish_date" column as shown in below table for (task_id "121690") with no values on fridays:

taskrsrc_idtask_idrsrc_idtarget_qtytarget_start_datetarget_end_date16-09-202017-09-202018-09-202019-09-202020-09-202021-09-202022-09-202023-09-202024-09-202025-09-202026-09-202027-09-202028-09-202029-09-202030-09-202001-10-202002-10-202003-10-2020
13030312169072501080016-09-202016-11-2020207.69207.69 207.69207.69207.69207.69207.69207.69 207.69207.69207.69207.69207.69207.69 207.69

Thanks,