Date when stock runs out and running totals

i have data in the below format. I would like to find running stock on hand from Total Stock - Cummulative requirement and then return the date when the stock is 0

 

part no.   Date required.  Total Stock.  CummReq

1234.      2022/11/10.      11977.              600

1234.      2022/11/11.                               600

1234.       2022/11/12.                               600

 

 

I would like to show the depletion of stock over time

 

2 ACCEPTED SOLUTIONS
Anonymous
Not applicable

Hi @Anonymous ,

 

According to your description, here are my steps you can follow as a solution.

(1)This is my test data.

vtangjiemsft_0-1668146113942.png

 

(2)We can create  a measure.

Measure = SUM('Table'[CummReq])

(3)We can create  calculated columns.

running stock =
CALCULATE (
    MAX ( 'Table'[Total Stock] ),
    FILTER (
        ALLEXCEPT ( 'Table', 'Table'[part no] ),
        'Table'[Date required] <= EARLIER ( 'Table'[Date required] )
    )
)
    - CALCULATE (
        'Table'[Measure],
        FILTER (
            ALLEXCEPT ( 'Table', 'Table'[part no] ),
            'Table'[Date required] <= EARLIER ( 'Table'[Date required] )
        )
    )
0 date = 
IF('Table'[running stock]<=0,'Table'[Date required],BLANK())

(3) Then the result is as follows.

vtangjiemsft_1-1668146113955.png

 

 

If the above one can't help you get the desired result, please provide some sample data in your tables (exclude sensitive data) with Text format and your expected result with backend logic and special examples. It is better if you can share a simplified pbix file. Thank you.

 

Best Regards,

Neeko Tang

If this post helps, then please consider Accept it as the solution to help the other members find it more quickly. 

View solution in original post

3 REPLIES 3
Anonymous
Not applicable

Hi @Anonymous ,

 

According to your description, here are my steps you can follow as a solution.

(1)This is my test data.

vtangjiemsft_0-1668146113942.png

 

(2)We can create  a measure.

Measure = SUM('Table'[CummReq])

(3)We can create  calculated columns.

running stock =
CALCULATE (
    MAX ( 'Table'[Total Stock] ),
    FILTER (
        ALLEXCEPT ( 'Table', 'Table'[part no] ),
        'Table'[Date required] <= EARLIER ( 'Table'[Date required] )
    )
)
    - CALCULATE (
        'Table'[Measure],
        FILTER (
            ALLEXCEPT ( 'Table', 'Table'[part no] ),
            'Table'[Date required] <= EARLIER ( 'Table'[Date required] )
        )
    )
0 date = 
IF('Table'[running stock]<=0,'Table'[Date required],BLANK())

(3) Then the result is as follows.

vtangjiemsft_1-1668146113955.png

 

 

If the above one can't help you get the desired result, please provide some sample data in your tables (exclude sensitive data) with Text format and your expected result with backend logic and special examples. It is better if you can share a simplified pbix file. Thank you.

 

Best Regards,

Neeko Tang

If this post helps, then please consider Accept it as the solution to help the other members find it more quickly. 

Anonymous
Not applicable

Thank you so much

Helpful resources

Announcements
FabCon Global Hackathon Carousel

FabCon Global Hackathon

Join the Fabric FabCon Global Hackathon—running virtually through Nov 3. Open to all skill levels. $10,000 in prizes!

September Power BI Update Carousel

Power BI Monthly Update - September 2025

Check out the September 2025 Power BI update to learn about new features.

FabCon Atlanta 2026 carousel

FabCon Atlanta 2026

Join us at FabCon Atlanta, March 16-20, for the ultimate Fabric, Power BI, AI and SQL community-led event. Save $200 with code FABCOMM.