Hi,
I am stuck in the below calculation , When I apply filter <= today it also counting blank
I need below result when i select a year (i.e 2021) in Slicer (Calendar Table)
Data set and pbix available in below link
https://drive.google.com/drive/folders/14JD2NuIVIZn7Muuem8KyPLxoEWVexzjO?usp=sharing
Solved! Go to Solution.
@ajisharavind_99 , Try like
CALCULATE(CALCULATE(
COUNTROWS( Sheet1 ),
USERELATIONSHIP( Dim_Calendar[Date] , Sheet1[Task Planned] )),
FILTER(
Dim_Calendar,
Dim_Calendar[Date]
<= TODAY()
)
)
or
CALCULATE(CALCULATE(
COUNTROWS( Sheet1 ),
USERELATIONSHIP( Dim_Calendar[Date] , Sheet1[Task Planned] )),
FILTER(
all(Dim_Calendar),
Dim_Calendar[Date]
<= TODAY()
)
)
----------------
CALCULATE(CALCULATE(
COUNTROWS( Sheet1 ),
USERELATIONSHIP( Dim_Calendar[Date] , Sheet1[Task Completed] )),
FILTER(
Dim_Calendar,
Dim_Calendar[Date]
<= TODAY()
)
)
or
CALCULATE(CALCULATE(
COUNTROWS( Sheet1 ),
USERELATIONSHIP( Dim_Calendar[Date] , Sheet1[Task Completed] )),
FILTER(
all(Dim_Calendar),
Dim_Calendar[Date]
<= TODAY()
)
)
@ajisharavind_99 , Try like
CALCULATE(CALCULATE(
COUNTROWS( Sheet1 ),
USERELATIONSHIP( Dim_Calendar[Date] , Sheet1[Task Planned] )),
FILTER(
Dim_Calendar,
Dim_Calendar[Date]
<= TODAY()
)
)
or
CALCULATE(CALCULATE(
COUNTROWS( Sheet1 ),
USERELATIONSHIP( Dim_Calendar[Date] , Sheet1[Task Planned] )),
FILTER(
all(Dim_Calendar),
Dim_Calendar[Date]
<= TODAY()
)
)
----------------
CALCULATE(CALCULATE(
COUNTROWS( Sheet1 ),
USERELATIONSHIP( Dim_Calendar[Date] , Sheet1[Task Completed] )),
FILTER(
Dim_Calendar,
Dim_Calendar[Date]
<= TODAY()
)
)
or
CALCULATE(CALCULATE(
COUNTROWS( Sheet1 ),
USERELATIONSHIP( Dim_Calendar[Date] , Sheet1[Task Completed] )),
FILTER(
all(Dim_Calendar),
Dim_Calendar[Date]
<= TODAY()
)
)