Hi all,
I have the following column, withthe year and the week number and I'm looking to convert this to a date where the date is the first date of the given week (ie 202304 would be 23/01/2023). Is this possible using DAX and perhaps a new column?
Any help would be much appreciated! Thanks
Solved! Go to Solution.
hi @Anonymous
try to add a column like this:
DATE = DATE( LEFT([YYYYMM], 4), 1,1) + (RIGHT([YYYYMM],2)-1)*7 + 1
hi @Anonymous
try to add a column like this:
DATE = DATE( LEFT([YYYYMM], 4), 1,1) + (RIGHT([YYYYMM],2)-1)*7 + 1
This worked, thank you so much!
Join the Fabric FabCon Global Hackathon—running virtually through Nov 3. Open to all skill levels. $10,000 in prizes!
Check out the October 2025 Power BI update to learn about new features.
| User | Count |
|---|---|
| 11 | |
| 9 | |
| 8 | |
| 6 | |
| 6 |