Hi,
I have the line chart below and we have data until 23 July but I want the graph to continue until 100% based on the previous speed of the graph.
It will be the prediction of when this will be finished. If you want to see what I mean in excel this is the chart in excel.
The blue line is the extension line.
We subtract %Completion of each day with the previous day and the average of all these days will be the average progress speed and I want to continue the line based on that number until it reaches 100%.
Is there a way that this can be acheived?
Solved! Go to Solution.
Another way I have just figured out.
Source data
Monthly Progress
Cumulative Progress
Cumulative Actual Progress
Cumulative Forecst Progress
Overall Graph
Another way I have just figured out.
Source data
Monthly Progress
Cumulative Progress
Cumulative Actual Progress
Cumulative Forecst Progress
Overall Graph
Hi you need to align the actual and forecast line in a single line. its possible. I am sharing my youtube video link
https://www.youtube.com/watch?v=hNU6M1yjz80&t=11s
also you can refer my S-Curve Playlist for the same.