Calculate Variance between last two complete weeks

Hello DAX Gods,

I have a visual here that compiles hours worked by each group displayed in a weekly basis. What I'm trying to accomplish is to calculate the variance between the last 2 "complete" weeks. For this example, I would like to calculate the difference between the Week of 3/31/2024 and 3/24/2024 since the current week (4/7/2024) is not yet complete. Just to clarify, on the timesheet table, there are already time entries for the week of 4/7/2024 but since that week is not yet complete, I don't want to use "current week".

 

How do I write the dax formula for this?

 

egrospe17_0-1712618197166.png

 

1 ACCEPTED SOLUTION
Anonymous
Not applicable

Hi @egrospe17 ,

The Table data is shown below(Today is April 9, 2024 and April 14, 2024 is an unfinished week):

vzhouwenmsft_0-1712629162621.png

Please follow these steps:

1. Use the following DAX expression to create a measure

Measure = 
VAR CurrentDay = TODAY()
VAR ISaWeek = WEEKDAY(CurrentDay,2)
VAR EndDay = IF(ISaWeek = 7,CurrentDay, CurrentDay - ISaWeek)
VAR StartDay = EndDay - 7
VAR _a = CALCULATE(SUM('Table'[Hour]),'Table'[Date] = StartDay)
VAR _b = CALCULATE(SUM('Table'[Hour]),'Table'[Date] = EndDay)
RETURN _b -_a

2.Final output

vzhouwenmsft_1-1712629335543.png

Best Regards,
Wenbin Zhou
If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.

View solution in original post

1 REPLY 1
Anonymous
Not applicable

Hi @egrospe17 ,

The Table data is shown below(Today is April 9, 2024 and April 14, 2024 is an unfinished week):

vzhouwenmsft_0-1712629162621.png

Please follow these steps:

1. Use the following DAX expression to create a measure

Measure = 
VAR CurrentDay = TODAY()
VAR ISaWeek = WEEKDAY(CurrentDay,2)
VAR EndDay = IF(ISaWeek = 7,CurrentDay, CurrentDay - ISaWeek)
VAR StartDay = EndDay - 7
VAR _a = CALCULATE(SUM('Table'[Hour]),'Table'[Date] = StartDay)
VAR _b = CALCULATE(SUM('Table'[Hour]),'Table'[Date] = EndDay)
RETURN _b -_a

2.Final output

vzhouwenmsft_1-1712629335543.png

Best Regards,
Wenbin Zhou
If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.

Helpful resources

Announcements
November Power BI Update Carousel

Power BI Monthly Update - November 2025

Check out the November 2025 Power BI update to learn about new features.

Fabric Data Days Carousel

Fabric Data Days

Advance your Data & AI career with 50 days of live learning, contests, hands-on challenges, study groups & certifications and more!

FabCon Atlanta 2026 carousel

FabCon Atlanta 2026

Join us at FabCon Atlanta, March 16-20, for the ultimate Fabric, Power BI, AI and SQL community-led event. Save $200 with code FABCOMM.