Burndown
Hey! How to Create a Scrum Sprint Tracking Chart My team has an existing report in Excel that I'm trying to revamp in Power BI that uses a burndown chart. Thanks in advance for any help Sprint tota...
KellSilveira
4 years agoFrequent Visitor
Hi
Complementing
Graphic
On the vertical axis, the sum of budgeted hours needed to carry out the activities of the current iteration (eg, sprint 22.23) and, on the horizontal axis, the work days of the iteration.
This graph is represented in two lines. The first is the ideal line (budgeted hours), straight, from top to bottom, representing the complete demand for work at the beginning of the project (top left) and going to the lowest point on the right, where the forecast completion of the sprint on the schedule.
The second is the actual line (in my case, hours executed), which reveals how the team behaved in relation to the projection of time usage for demand during the sprint selected in the segmentation.