Burndown chart for data progress
I've found a few instances of using a burndown chart in TFS and Scrum settings, but my team has an existing report in SSRS that I'm trying to remodel in Power BI that utilizes a burndown chart for project progress for data migration. I have several projects in a Projects table, and all the transaction data in a Transactions table for migrated data. This leads me to two questions:
1) I have the expected number of items in the Projects table and the total number of items completed in the Transactions table. Do I need to create a new table with calculated data? If so, will this account for slicing to different projects?
2) I also need to show the estimated date of completion based on an average of the Actual data migrated over the past 2 weeks. How will I calculate this?
Thanks in advance for any help. I'm still pretty new to Power BI so a lot of this escapes me for now. I've included an example of the current chart below.
- Anonymous9 years ago
Hi boclifton,
You can try to use below formulas to get the remain item and bytes.
Measures:
Remain Items =
var currProject=LASTNONBLANK(Table[ProjectID],[ProjectID])
var TotalItem=SUMX(FILTER(ALL(Table),Table[ProjectID]=currProject),[TransactionItemsMigrated]) + MAX(Table[CurrentItemFailed]) //total items + failed items
return
TotalItem-SUMX(FILTER(ALL(Table),Table[ProjectID]=currProject&&Table[Date]<=MAX(Table[Date])),[TransactionItemsMigrated])Remain Bytes =
var currProject=LASTNONBLANK(Table[ProjectID],[ProjectID])
var TotalBytes=SUMX(FILTER(ALL(Table),Table[ProjectID]=currProject),[TransactionSizeBytes])
return
TotalBytes-SUMX(FILTER(ALL(Table),Table[ProjectID]=currProject&&Table[Date]<=MAX(Table[Date])),[TransactionSizeBytes])Regards,
Xiaoxin Sheng