Hi,
I have a 2 numbers, Labor Cost Budget & Labor Cost Actual-To-Date. I am trying to show a 3rd number which is Projected Labor Cost at Year End. Right now i am trying to use Bar Charts, but there is no forecasting option under the Analytics tab. Is there a way to make Power Bi calculate and display the Project Number at Year end?
Thank you Chris.
Hi,
As I know, using of Analytic Tab is limited and it works only for core visuals for a while.
However, you could try some of the custom bar charts to cover your task as this one or that one, for instance, or look for other bar chart variants in the store.
Kind Regards,
Evgenii Elkin,
Software Engineer
Microsoft Power BI Custom Visuals
pbicvsupport@microsoft.com
If you have recently started exploring Fabric, we'd love to hear how it's going. Your feedback can help with product improvements.
A new Power BI DataViz World Championship is coming this June! Don't miss out on submitting your entry.
Share feedback directly with Fabric product managers, participate in targeted research studies and influence the Fabric roadmap.