Join us at FabCon Atlanta from March 16 - 20, 2026, for the ultimate Fabric, Power BI, AI and SQL community-led event. Save $200 with code FABCOMM.
Register now!Calling all Data Engineers! Fabric Data Engineer (Exam DP-700) live sessions are back! Starting October 16th. Sign up.
Alright boys, girls, and malfunctioning automata, I have a conudrum that I would like some assistance resolving.
In image 1, is the table in my dashboard that honestly needs some work.
What I would like to do is add a seperater column inbetween each COLO that simply states the COLO that is to follow. Or some way to break each COLO into sections within the table so their is a visual break in the data.
The data the table uses itself is fairly simple:
COLO 1 | L1 Cx Start | 12/19/2024 | 12/23/2024 | 2 |
COLO 1 | L1 Cx Finish | 2/26/2025 | 1/31/2025 | -18 |
COLO 1 | L2 CX Start | 2/27/2025 | 1/31/2025 | -19 |
COLO 1 | L2 Cx Finish | 5/7/2025 | 4/17/2025 | -14 |
COLO 1 | L3 Cx Start | 5/8/2025 | 4/18/2025 | -14 |
COLO 1 | L3 Cx Finish | 7/3/2025 | 6/13/2025 | -14 |
COLO 1 | L4 Cx Start | 7/5/2025 | 6/14/2025 | -17 |
COLO 1 | L4 Cx Finish | 8/4/2025 | 7/15/2025 | -17 |
COLO 1 | L5 Cx Start | 8/5/2025 | 7/18/2025 | -15 |
COLO 1 | L5 Cx Finish | 8/6/2025 | 7/19/2025 | -15 |
COLO 2 | L1 Cx Start | 2/10/2025 | 1/9/2025 | -22 |
COLO 2 | L1 Cx Finish | 2/28/2025 | 1/29/2025 | -22 |
COLO 2 | L2 CX Start | 4/17/2025 | 4/2/2025 | -11 |
COLO 2 | L2 Cx Finish | 6/27/2025 | 6/13/2025 | -10 |
COLO 2 | L3 Cx Start | 6/30/2025 | 6/16/2025 | -10 |
COLO 2 | L3 Cx Finish | 8/18/2025 | 8/4/2025 | -10 |
COLO 2 | L4 Cx Start | 8/19/2025 | 8/5/2025 | -12 |
COLO 2 | L4 Cx Finish | 9/13/2025 | 8/29/2025 | -12 |
COLO 2 | L5 Cx Start | 9/13/2025 | 8/30/2025 | -11 |
COLO 2 | L5 Cx Finish | 9/15/2025 | 9/2/2025 | -11 |
COLO 3 | L1 Cx Start | 3/12/2025 | 4/1/2025 | 14 |
COLO 3 | L1 Cx Finish | 5/20/2025 | 5/1/2025 | -14 |
COLO 3 | L2 CX Start | 6/5/2025 | 5/23/2025 | -8 |
COLO 3 | L2 Cx Finish | 8/21/2025 | 8/11/2025 | -8 |
COLO 3 | L3 Cx Start | 8/22/2025 | 8/12/2025 | -8 |
COLO 3 | L3 Cx Finish | 10/10/2025 | 9/30/2025 | -8 |
COLO 3 | L4 Cx Start | 10/11/2025 | 10/1/2025 | -9 |
COLO 3 | L4 Cx Finish | 11/6/2025 | 10/27/2025 | -9 |
COLO 3 | L5 Cx Start | 11/7/2025 | 10/28/2025 | -9 |
COLO 3 | L5 Cx Finish | 11/8/2025 | 10/29/2025 | -9 |
COLO 4 | L1 Cx Start | 4/2/2025 | 7/7/2025 | 66 |
COLO 4 | L1 Cx Finish | 7/3/2025 | 7/7/2025 | 1 |
COLO 4 | L2 CX Start | 7/15/2025 | 7/8/2025 | -5 |
COLO 4 | L2 Cx Finish | 10/6/2025 | 9/29/2025 | -5 |
COLO 4 | L3 Cx Start | 10/8/2025 | 10/1/2025 | -5 |
COLO 4 | L3 Cx Finish | 11/25/2025 | 11/18/2025 | -5 |
COLO 4 | L4 Cx Start | 11/26/2025 | 11/19/2025 | -6 |
COLO 4 | L4 Cx Finish | 12/23/2025 | 12/16/2025 | -5 |
COLO 4 | L5 Cx Start | 12/24/2025 | 12/17/2025 | -6 |
COLO 4 | L5 Cx Finish | 12/26/2025 | 12/18/2025 | -6 |
COLO 5 | L1 Cx Start | 4/16/2025 | 8/12/2025 | 82 |
COLO 5 | L1 Cx Finish | 8/27/2025 | 7/17/2025 | -30 |
COLO 5 | L2 CX Start | 9/10/2025 | 9/9/2025 | -1 |
COLO 5 | L2 Cx Finish | 11/25/2025 | 11/24/2025 | -1 |
COLO 5 | L3 Cx Start | 11/26/2025 | 11/26/2025 | 0 |
COLO 5 | L3 Cx Finish | 1/16/2026 | 1/16/2026 | 0 |
COLO 5 | L4 Cx Start | 1/17/2026 | 1/17/2026 | 0 |
COLO 5 | L4 Cx Finish | 2/11/2026 | 2/11/2026 | 0 |
COLO 5 | L5 Cx Start | 2/12/2026 | 2/12/2026 | 0 |
COLO 5 | L5 Cx Finish | 2/13/2026 | 2/13/2026 | 0 |
What I'm looking for is something similiar to the excel table below but with the L1 and L2s called out like in the example up top.
Have you considered using paginated reports for this?
Join the Fabric FabCon Global Hackathon—running virtually through Nov 3. Open to all skill levels. $10,000 in prizes!
Check out the October 2025 Power BI update to learn about new features.
User | Count |
---|---|
8 | |
2 | |
2 | |
2 | |
1 |