How to calculate project progress using start date and end date

  • Hi, Ykankam 

    Please try formulas like:

    Percentage% =
    VAR a =
        CALCULATE (
            COUNTROWS ( 'Table' ),
            FILTER ( 'Table', 'Table'[Project] = EARLIER ( 'Table'[Project] ) )
        )
    VAR b =
        CALCULATE (
            COUNTROWS ( 'Table' ),
            FILTER (
                'Table',
                'Table'[Project] = EARLIER ( 'Table'[Project] )
                    && 'Table'[Due Status] = "Not Overdue"
            )
        )
    RETURN
        b / a
    

    or measure

    Percentage1% = 
    VAR a =
        CALCULATE (
            COUNTROWS ( 'Table' ),
            FILTER ( ALLSELECTED('Table'), 'Table'[Project] = max( 'Table'[Project] ) )
        )
    VAR b =
        CALCULATE (
            COUNTROWS ( 'Table' ),
            FILTER (
                ALLSELECTED('Table'),
                'Table'[Project] = MAX( 'Table'[Project] )
                    && 'Table'[Due Status] = "Not Overdue"
            )
        )
    RETURN
        b/a+0

    If it doesn't work, please share a sample file and expected result for further research.

    Best Regards,
    Community Support Team _ Eason

     

4 Replies

  • From the image above. I have a list of projects with start date and end date. Each project has a status.

    Now I want a column that will calculate the aggregated completion rate(percentage) for each project base on the start date and end date.

    • v-easonf-msft's avatar
      v-easonf-msft
      Community Support

      Hi, Ykankam 

      Please try formulas like:

      Percentage% =
      VAR a =
          CALCULATE (
              COUNTROWS ( 'Table' ),
              FILTER ( 'Table', 'Table'[Project] = EARLIER ( 'Table'[Project] ) )
          )
      VAR b =
          CALCULATE (
              COUNTROWS ( 'Table' ),
              FILTER (
                  'Table',
                  'Table'[Project] = EARLIER ( 'Table'[Project] )
                      && 'Table'[Due Status] = "Not Overdue"
              )
          )
      RETURN
          b / a
      

      or measure

      Percentage1% = 
      VAR a =
          CALCULATE (
              COUNTROWS ( 'Table' ),
              FILTER ( ALLSELECTED('Table'), 'Table'[Project] = max( 'Table'[Project] ) )
          )
      VAR b =
          CALCULATE (
              COUNTROWS ( 'Table' ),
              FILTER (
                  ALLSELECTED('Table'),
                  'Table'[Project] = MAX( 'Table'[Project] )
                      && 'Table'[Due Status] = "Not Overdue"
              )
          )
      RETURN
          b/a+0

      If it doesn't work, please share a sample file and expected result for further research.

      Best Regards,
      Community Support Team _ Eason

       

      • Ykankam's avatar
        Ykankam
        Helper I

        v-easonf-msft VahidDM  thank you both. It worked.

         

        How do create a dax formula to show all projects startinng next month and another one to show all projects ending this month?